- Practice · 5 marks
MRP II closed loop system
Short answer
MRP II is a company-wide closed-loop system that plans all manufacturing resources—materials, capacity, labour, and money—linking production with marketing and finance. Unlike MRP, it checks capacity and includes financial planning. Main modules: business/sales plan, MPS, MRP, CRP, shop-floor control/purchasing, and finance/simulation.
What is MRP II (Manufacturing Resource Planning)? Explain how it differs from MRP and describe its main modules.
MRP II extends MRP into a company-wide system that plans all the resources of a manufacturing firm: materials, capacity, labour, machines and money. It links production planning with marketing and finance and uses a common database. It is called "closed loop" because feedback from shop floor and suppliers is used to revise plans.
Main modules
Business plan -> Sales & operations plan
|
Master Production Schedule (MPS) -> Rough-cut capacity
|
MRP (material plan) -> Capacity requirements planning
|
Shop-floor control & purchasing
| (feedback to upper levels)
- Business and sales/production planning: long-range plan in money and units.
- Master production schedule and rough-cut capacity planning.
- MRP: time-phased material plan.
- Capacity requirements planning (CRP): checks that machines and labour can meet the MRP plan.
- Shop-floor control and purchasing: dispatching, order release and supplier control.
- Finance, costing and simulation: cost, budgets and "what-if" analysis.
MRP versus MRP II
| Basis | MRP | MRP II |
|---|---|---|
| Scope | Material planning only | All manufacturing resources |
| Capacity | Assumed infinite | Checked by CRP |
| Money | Not included | Financial planning included |
| Feedback | Limited | Closed loop |
| Integration | Production only | Marketing, finance, engineering, production |
The later extension is ERP, which covers the whole enterprise including HR and accounts.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- MRP concept, inputs and outputs · Industrial Engineering and Management, chapter 5
- Closed loop MBI system · Instrumentation II, chapter 1 · asked 2×
- Define control system and closed loop block roles · Control Systems, chapter 1 · asked 5×
- Closed loop control system block diagram explained · Control Systems, chapter 1 · asked 4×
- Steps to design closed loop control system · Embedded System, chapter 7
All Industrial Engineering and Management chapter 5 questions →