- Practice · 6 marks
MRP concept, inputs and outputs
Short answer
MRP converts master schedule into time-phased material requirements using BOM and inventory data. Inputs: MPS, BOM, inventory records. Outputs: planned order releases, rescheduling notices, reports. Benefits: lower inventory, better delivery, fewer stockouts. Used in assembly industries.
Explain the concept of Material Requirement Planning (MRP). Describe its inputs, outputs, benefits and applications.
MRP is a computer-based planning system that converts the master production schedule of end products into time-phased requirements of the sub-assemblies, components and raw materials. It answers: what to order, how much, and when. It is used for dependent demand items (items whose demand depends on the end product), unlike reorder-point systems for independent demand.
Inputs
Master Production Bill of Materials Inventory records
Schedule (MPS) (BOM) (on hand, on order)
\ | /
+--------> MRP LOGIC <-------------+
|
Planned order releases | Reschedule notices | Reports
- Master production schedule (MPS): quantity and date of each end product.
- Bill of materials (BOM): product structure showing parts per unit at each level.
- Inventory status file: on-hand stock, scheduled receipts, lead times, lot-size rules and safety stock.
Working
Gross requirements are exploded level by level; net requirements are found as gross minus (on hand + scheduled receipts); orders are planned and offset backward by the lead time.
Outputs
- Planned order releases (what to order and when).
- Order rescheduling notices (move earlier or later).
- Cancellation notices and exception reports.
- Inventory and performance reports.
Benefits
- Lower inventory and work-in-process.
- Better delivery performance and customer service.
- Fewer stock-outs and rush orders.
- Better use of labour and machines; realistic schedules.
- Quick response to change in MPS.
Applications
Assembly industries with many components and long lead times: machinery, automobiles, electronics, aircraft, furniture.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- MRP II closed loop system · Industrial Engineering and Management, chapter 5
- Charter tools, inputs and outputs · ICT Project Management, chapter 7
- Benefits and problems of reuse; reuse planning · Software Engineering, chapter 5
- DSM concept; planning and implementation steps · Utilization of Electrical Energy, chapter 6
- Capital structure planning concept · Project Engineering, chapter 6 · asked 2×
All Industrial Engineering and Management chapter 5 questions →