Charter tools, inputs and outputs

Short answer

Inputs are the project statement of work, business case, agreement, enterprise environmental factors, and organizational process assets. Tools include expert judgment and facilitation techniques. The output is the project charter that authorizes the project and details high-level requirements.

Explain necessary tools and techniques, input and output to develop the project charter.

The Develop Project Charter process (PMBOK, Integration Management, Initiating group) authorises the project and documents the initial requirements. Its main elements are as follows.

 Inputs                 Tools             Output
 SOW                    Expert judgment   Project
 Business case    -->   Facilitation -->  charter
 Agreement/contract     techniques
 EEF, OPA

Inputs

  1. Project statement of work (SOW): a narrative description of the products or services to be delivered; it covers the business need, product scope description and strategic plan.
  2. Business case: justification showing the need for the project and its financial benefit (cost-benefit analysis).
  3. Agreement: a contract with the customer, if the project is for an external customer.
  4. Enterprise environmental factors (EEF): government standards, industry rules, market conditions, organisational culture and structure.
  5. Organisational process assets (OPA): standard processes, templates, policies, historical information and lessons learned.

Tools and techniques

  1. Expert judgment: advice from experts, consultants, stakeholders, the PMO or professional bodies about technical details, cost, risk and similar projects.
  2. Facilitation techniques: brainstorming, conflict resolution, problem solving and meeting management to obtain stakeholders' agreement on the charter content.
  3. Selection methods and SWOT analysis may also support the decision to start.

Output

Project charter: it records business needs, assumptions, constraints, high-level requirements, objectives, summary schedule and budget, and gives the project manager authority.

Importance

The charter links the project to strategic aims, gives formal authority and forms the basis for the project scope statement and the rest of planning.

Example: For an e-governance portal, the SOW (from the ministry), the business case (it saves citizens' time) and the contract with the vendor are inputs; experts review the proposal, and the sponsor signs the charter.