Charter tools, inputs and outputs
Short answer
Inputs are the project statement of work, business case, agreement, enterprise environmental factors, and organizational process assets. Tools include expert judgment and facilitation techniques. The output is the project charter that authorizes the project and details high-level requirements.
Explain necessary tools and techniques, input and output to develop the project charter.
The Develop Project Charter process (PMBOK, Integration Management, Initiating group) authorises the project and documents the initial requirements. Its main elements are as follows.
Inputs Tools Output
SOW Expert judgment Project
Business case --> Facilitation --> charter
Agreement/contract techniques
EEF, OPA
Inputs
- Project statement of work (SOW): a narrative description of the products or services to be delivered; it covers the business need, product scope description and strategic plan.
- Business case: justification showing the need for the project and its financial benefit (cost-benefit analysis).
- Agreement: a contract with the customer, if the project is for an external customer.
- Enterprise environmental factors (EEF): government standards, industry rules, market conditions, organisational culture and structure.
- Organisational process assets (OPA): standard processes, templates, policies, historical information and lessons learned.
Tools and techniques
- Expert judgment: advice from experts, consultants, stakeholders, the PMO or professional bodies about technical details, cost, risk and similar projects.
- Facilitation techniques: brainstorming, conflict resolution, problem solving and meeting management to obtain stakeholders' agreement on the charter content.
- Selection methods and SWOT analysis may also support the decision to start.
Output
Project charter: it records business needs, assumptions, constraints, high-level requirements, objectives, summary schedule and budget, and gives the project manager authority.
Importance
The charter links the project to strategic aims, gives formal authority and forms the basis for the project scope statement and the rest of planning.
Example: For an e-governance portal, the SOW (from the ministry), the business case (it saves citizens' time) and the contract with the vendor are inputs; experts review the proposal, and the sponsor signs the charter.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Project charter · ICT Project Management, chapter 7
- Information in a project charter · ICT Project Management, chapter 7
- Expert judgment in project charter · ICT Project Management, chapter 7
- Cost estimating tools · ICT Project Management, chapter 9
- Project verification and inspection · ICT Project Management, chapter 7
- Risk identification techniques · ICT Project Management, chapter 12
- MRP concept, inputs and outputs · Industrial Engineering and Management, chapter 5
- Tools and techniques for risk identification · Project Engineering, chapter 5 · asked 2×
- Animation techniques and software tools · Multimedia System, chapter 4
- Techniques of project formulation · Project Engineering, chapter 2 · asked 3×