- Year not given
Expert judgment in project charter
Short answer
Expert judgment uses specialised knowledge to develop the project charter by advising on strategic alignment, feasibility, high-level estimates, risk identification, and regulatory compliance. Sources include internal units, consultants, and stakeholders to ensure the charter is realistic and complete.
How expert judgment is useful in developing project charter?
Expert judgment is judgment provided on the basis of expertise in an application area, knowledge area, discipline or industry, as suitable for the activity being performed. It is a tool and technique of the Develop Project Charter process (and many others) in PMBOK. Experts may be groups or individuals with specialised knowledge or training.
Sources of expert judgment
- Other units within the organisation.
- Consultants.
- Stakeholders, including customers and sponsors.
- Professional and technical associations.
- Industry groups and subject matter experts.
- The Project Management Office (PMO).
How it is useful in developing the charter
- Understanding the business case and strategy: experts advise whether the project aligns with business goals and the organisation's strategic plan.
- Technical feasibility: specialists indicate whether the proposed technology is suitable, e.g. cloud versus on-premise.
- Realistic estimates: experienced managers provide high-level cost, time and resource estimates, using similar past projects.
- Risk identification: experts point out likely risks and constraints early.
- Legal and regulatory compliance: legal, finance and industry experts note necessary approvals and standards.
- Selecting stakeholders and understanding their needs.
- Review and refinement: experts review the draft charter for completeness and clarity.
- Using organisational knowledge: they apply knowledge of OPAs (templates, lessons learned).
Experts --> advice --> Develop Charter --> Charter
Precautions
Judgment may be biased or opinionated; verify with data, use several experts and document assumptions.
Example: For a core banking migration, the sponsor consults a senior database consultant and the compliance officer. They help set a realistic 12-month schedule and highlight Nepal Rastra Bank regulatory requirements in the charter.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Project charter · ICT Project Management, chapter 7
- Information in a project charter · ICT Project Management, chapter 7
- Charter tools, inputs and outputs · ICT Project Management, chapter 7
- Baseline management in project plan · ICT Project Management, chapter 7
- IT project management methodology · ICT Project Management, chapter 14
- Procedure for developing a project proposal · Project Engineering, chapter 2 · asked 4×
- 300 MW reservoir project: planning to commissioning · Hydropower Engineering, chapter 2
- Modified B/C ratio for 100,000 project · Engineering Economics, chapter 3
- Best project for 4-year and 8-year service periods · Engineering Economics, chapter 4