Baseline management in project plan

Short answer

Baseline management establishes approved scope, schedule, and cost baselines as reference points for performance measurement. It enables variance analysis, earned value management, prevents scope creep through formal change control, and supports forecasting and accountability.

How is baseline management useful in developing a project management plan?

A baseline is the approved version of a plan (scope, schedule or cost) that can be changed only through formal change control, and is used as a basis for comparison. Baseline management means creating, approving, protecting and updating baselines so that actual performance can be measured against them. It is a vital part of the project management plan.

Main baselines

  • Scope baseline: approved scope statement, WBS and WBS dictionary.
  • Schedule baseline: approved schedule with start and finish dates.
  • Cost baseline: approved time-phased budget (used for earned value).
  • Together these are called the performance measurement baseline.
  • Other baselines: quality, requirements, configuration.
Plan -> Approve -> BASELINE -> Compare with actuals
                       ^            |
                       +- Change control (approved changes)

Usefulness in developing the project management plan

  1. Reference for control: variance = actual − baseline; shows deviations in time, cost and scope.
  2. Earned value management requires a cost baseline.
  3. Clear agreement between sponsor, manager and team about what was planned.
  4. Prevents scope creep: any change must go through integrated change control, and the baseline is updated only with approval.
  5. Helps forecasting (EAC, completion date).
  6. Version control: previous baselines are kept to review history and for lessons learned.
  7. Accountability: the team knows the target they will be judged against.
  8. Supports configuration management by fixing the approved versions of documents and software.

Rebaselining

When a major approved change happens (e.g. the customer changes scope), a new baseline is set and the old one is retained for records. Frequent rebaselining hides poor performance and should be avoided.

Example: A web project has a baseline of 6 months and Rs 10 lakh. After 3 months the actual cost is Rs 6.5 lakh against a planned Rs 5 lakh, which shows a cost overrun against the baseline and prompts corrective action.