Information in a project charter

Short answer

A project charter includes the project title, business case, measurable objectives, project manager with authority, summary scope and deliverables, milestones, budget, success criteria, assumptions, constraints, high-level risks, and sponsor signature.

What type of information should be included while making a project charter?

A project charter should contain enough high-level information for management to authorise the project and for the project manager to start planning. The following information is usually included.

Information to include

  1. Project title and identification: name, number, date.
  2. Project purpose / justification (business case): the business need, problem or opportunity and the expected benefits.
  3. Project objectives: specific, measurable, achievable, realistic and time-bound (SMART).
  4. Project manager and authority: name, responsibility, authority level (e.g. spending limit, staffing rights).
  5. Project sponsor and key stakeholders: names and roles.
  6. High-level requirements and description of the product or service.
  7. Scope and major deliverables: what is included and excluded.
  8. Summary milestones and schedule: start date, key milestones and end date.
  9. Summary budget: estimated total cost and funding source.
  10. Success criteria: how the project will be judged, e.g. approval by customer, benefits achieved.
  11. Assumptions and constraints: assumed conditions and limits on time, cost, resources, technology.
  12. High-level risks.
  13. Approval requirements: who signs off, what is needed for completion.
  14. Signatures of sponsor and manager.

Example (Library Management System)

ItemEntry
ObjectiveComputerise book issue and return in 5 months
BudgetRs 12 lakh
DeliverablesSoftware, user manual, staff training
MilestonesDesign: Month 2; Testing: Month 4; Go-live: Month 5
RiskStaff resistance
SponsorPrincipal

The information must be brief and clear and agree with the SOW and business case. Details are added later in the scope statement and project management plan.