- Asked 2/20
- 2072 Magh · 16 marks
Drawing hall 40 × 25 × 6 m, 90 lm/m² LED
Short answer
Needed 45 W LED luminaires: 35, arranged 7×5. Lumen method: MF=1/1.2=0.833; φ=4050 lm; required lumens = 90×1000×1.2/0.8 = 135000 lm; N = 33.33, rounded up for spacing limit. Six light circuits (6 A MCB) and six power circuits (20 A MCB); DB: 32 A TPN MCB.
A drawing hall 40 m × 25 m × 6 m high is to be illuminated LED lamps to an average lux is 90 lm/m² on a working plane 1 m above the floor. Estimate suitable number of lamps. Assume coefficient of utilization of 0.8 depreciation factor of 1.2 and spacing / height ratio of 1.2.
| Size of lamps | 45 W |
|---|---|
| Luminous efficiency (in lm/W) | 90 |
Draw layout diagram showing arrangement of luminaries, switches, power socket and design the distribution board, if the supply system is 3-φ, 4-wire system.
Given: hall 40 m × 25 m × 6 m, E = 90 lm/m² on a plane 1 m above floor, CU = 0.8, depreciation factor 1.2, SHR = 1.2, 45 W LED at 90 lm/W, 3-phase 4-wire supply. Assumptions: luminaires mounted on the ceiling, so Hm = 6 − 1 = 5 m; pf 0.9; 12 power sockets of 16 A (1 kW each).
Number of luminaires
Lumen method: N = (E × A) / (φ × UF × MF), where φ is the output of one luminaire.
Area A = 40 × 25 = 1000 m²
φ per luminaire = 45 W × 90 lm/W = 4050 lm
MF = 1/DF = 1/1.2 = 0.833
Total lumens = E × A × DF / UF
= 90 × 1000 × 1.2 / 0.8
= 135000 lm
N = 135000 / 4050 = 33.33
Rounding up and fitting a regular grid: 7 × 5 = 35 luminaires (7 along the 40 m side, 5 along the 25 m side).
Arrangement and spacing
Spacing along length = 40/7 = 5.71 m
Spacing along width = 25/5 = 5 m
End spacing (to wall) = half of these
Max spacing = SHR × Hm = 1.2 × 5 = 6 m
5.71 m and 5 m ≤ 6 m → OK
Actual E = 35 × 4050 × 0.8 × 0.833 / 1000
= 94.5 lux (≥ 90 lux required)
Here the spacing limit (SHR 1.2) decides the grid: 34 lamps are needed for lux, and 7 × 5 = 35 just satisfies spacing ≤ 6 m. If the lamps were suspended 1 m (Hm = 4 m), spacing ≤ 4.8 m would need a 9 × 6 = 54 grid, so ceiling mounting is chosen.
Layout diagram
Plan 40 m × 25 m (letter = phase of lamp circuit)
+---------------+
| R R R R R R Y |
| B B Y Y Y Y Y |
| B B B B R R R |
| Y Y Y Y R R R |
| Y Y B B B B B |
+---------------+
[DB] [SB] <- entrance: DB and switch board
S S S S ... one switch per sub-circuit
Each light sub-circuit is controlled by one 6 A one-way switch; all switches are grouped on a switch board (SB) next to the entrance, and the DB is mounted beside it. Power sockets (16 A, 3-pin, with earth) are placed along the walls at about 1 m height, spaced roughly evenly.
Sub-circuits
Rule (IS 732 / NEA practice): a light sub-circuit carries at most 10 points and 800 W. Here one luminaire is 45 W, so up to 10 luminaires per sub-circuit. Number of circuits is made a multiple of 3 for phase balance.
| Circuit | Luminaires | Load (W) | Current (A) | Phase | MCB |
|---|---|---|---|---|---|
| L1 | 6 | 270 | 1.3 | R | 6 A |
| L2 | 6 | 270 | 1.3 | Y | 6 A |
| L3 | 6 | 270 | 1.3 | B | 6 A |
| L4 | 6 | 270 | 1.3 | R | 6 A |
| L5 | 6 | 270 | 1.3 | Y | 6 A |
| L6 | 5 | 225 | 1.09 | B | 6 A |
Power sub-circuits (assumed): 12 sockets of 16 A, each taken as 1 kW, at most 2 sockets per power sub-circuit (IS 732), 2.5 mm² Cu wire, 20 A MCB.
| Circuit | Sockets | Load (W) | Phase | MCB |
|---|---|---|---|---|
| P1 | 2 | 2000 | R | 20 A |
| P2 | 2 | 2000 | Y | 20 A |
| P3 | 2 | 2000 | B | 20 A |
| P4 | 2 | 2000 | R | 20 A |
| P5 | 2 | 2000 | Y | 20 A |
| P6 | 2 | 2000 | B | 20 A |
Distribution board design
| Phase | Circuits | Load (W) | Current (A) |
|---|---|---|---|
| R | L1, L4, P1, P4 | 4540 | 21.93 |
| Y | L2, L5, P2, P5 | 4540 | 21.93 |
| B | L3, L6, P3, P6 | 4495 | 21.71 |
Connected load = 1575 W light + 12000 W power = 13575 W
Most loaded phase = 4540 W
Iph = 4540 / (230 × 0.9) = 21.93 A
Main MCB ≥ 1.25 × 21.93 = 27.42 A → 32 A TPN MCB
DB specification: 6-way-per-phase TPN DB (18 ways in all, spares included) with 32 A TPN MCB as incomer, 40 A 4-pole RCCB (100 mA) for earth-leakage protection, 6 A SP MCBs (B-curve) for light circuits and 20 A SP MCBs for power circuits. Incoming cable: 4-core 6 mm² Cu PVC (rating 45 A ≥ 32 A), plus earth continuity conductor.
3-phase, 400/230 V, 4-wire supply
|
[Energy meter]
|
[32 A TPN MCB]
|
[40 A 4P RCCB]
|
==R====Y====B====N== busbars
| | | | |
L1 L2 L3 P1 P2 ...
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Drawing hall 40 × 25 × 6 m, 250 lux LED · Industrial Power Distribution and Illumination, chapter 7 · asked 3×
- Drawing hall 40 × 25 × 6 m, 2×36 W fluorescent · Industrial Power Distribution and Illumination, chapter 7
- Drawing hall 40 × 20 × 6 m lighting design · Industrial Power Distribution and Illumination, chapter 7 · asked 2×
- Factory hall 55.75 m × 40.25 m LED lighting · Industrial Power Distribution and Illumination, chapter 7 · asked 4×
- Industrial shop 30 × 25 m LED lighting · Industrial Power Distribution and Illumination, chapter 7
All Industrial Power Distribution and Illumination chapter 7 questions →