Purpose of earthing, earthed vs unearthed system

Short answer

The major purpose is to protect people by keeping enclosures near earth potential and to ensure fast fault clearance. In an earthed system, a fault causes a large current that trips protection, while an unearthed system allows supply to continue but causes healthy phases to rise to line voltage and may produce transient overvoltages.

What is the major purpose of earthing? Describe the consequences of earth and unearthed system.

Major purpose of earthing

Earthing connects the system neutral and the exposed metal parts of equipment to earth through a low-resistance path. Its main purposes are:

  • Safety of persons: keeps metal bodies near earth potential so a fault does not cause a dangerous shock.
  • Quick fault clearance: a large earth-fault current makes fuses, MCBs and relays trip quickly.
  • Stable system voltage: the earthed neutral fixes phase-to-earth voltage and limits overvoltages.
  • Safe discharge of lightning and static charges.

Consequences of earthed and unearthed systems

PointEarthed systemUnearthed system
Fault current on first earth faultLarge; protection tripsVery small (capacitive); nothing trips
Shock riskLow; faulty part isolated fastHealthy phases rise to line voltage; shock risk from second fault
Voltage of healthy phasesStays near phase voltageRises to √3 × phase voltage
OvervoltagesLimitedArcing ground gives transient overvoltages up to 5–6 times normal
Fault locationEasy (relay shows faulty feeder)Difficult
Continuity of supplyFeeder trips on first faultSupply can continue after one fault
Insulation neededPhase voltage levelLine voltage level (costlier)

Summary: an earthed system is safer and is used for almost all LV industrial and building installations. An unearthed system gives continuity during a single fault, but causes overvoltage, insulation stress, arcing grounds and hidden faults, so it is used only in special cases (some mines and process plants with insulation monitoring).