Substation site criteria and H-pole BOQ

Short answer

Site must be near load centre, accessible with firm ground and safe surroundings. A typical 11/0.4 kV 50 kVA H-pole substation BoQ includes transformer, two poles, platform channels, arresters, fuses, AB switch, insulators, conductors, LT distribution box, cables, earthing sets, stay set, danger plate, concrete foundation and labour.

Explain about site evaluation criteria of Substation. Also, prepare a Bill of Quantity of 11/0.4kV 50 kVA H-Pole Distribution Substation.

Site evaluation criteria for a substation

  1. Near the load centre: reduces LT cable length, voltage drop, losses and copper cost.
  2. Access to the HT line: close to the 11 kV feeder route so the HT tap is short.
  3. Accessibility: road access for transporting the transformer and for maintenance and fire-fighting vehicles.
  4. Ground conditions: firm, level, non-flooding land; low soil resistivity for good earthing.
  5. Safety: away from fuel stores, chemicals, explosive areas, schools and crowded places; enough clearance from buildings and trees.
  6. Space: enough area for the present equipment, future expansion, fencing and working clearance.
  7. Environment: free from dust, corrosive fumes and salt spray (otherwise choose indoor type); good natural ventilation.
  8. Cost and legal issues: land cost, right-of-way, approval of the utility and local bodies.
  9. Aesthetics and noise: transformer noise and appearance in residential surroundings.

Bill of quantities: 11/0.4 kV, 50 kVA H-pole substation (typical)

S.N.ItemUnitQty
1Distribution transformer 50 kVA, 11/0.4 kV, Dyn11, ONANNo.1
2PSC / steel tubular pole, 11 mNo.2
3MS channel (100 × 50 mm) for transformer platform and cross-armsSet1
411 kV lightning arrester, 9 kV, 5 kANo.3
511 kV drop-out fuse unit with fuse linksSet3
611 kV AB switch, gang operated, 200 ASet1
711 kV pin insulators with pinsNo.6
811 kV disc insulators with hardwareSet3–6
9HT jumper conductor (ACSR Dog/Rabbit)m30
10LT distribution box with MCCB 100 A (or fuse units), busbarsNo.1
11LT cable 1.1 kV, 3½ core 35 mm² Al XLPE (transformer to LT box)m15
12LT shackle / spool insulatorsNo.8
13Earthing sets (pipe/plate electrode, GI strip/wire, chamber)Set3
14GI earth wire 8 SWGkg20
15Stay set complete with stay wire and insulatorSet2
16Danger plate and anti-climbing deviceSet2
17Bolts, nuts, clamps, lugs, connectorsLot1
18Concrete for pole foundationm³1.5
19Labour, transport, testing and commissioningJob1

Three separate earths are provided: one for the transformer neutral, one for the transformer body and metal parts, and one for the lightning arresters. Quantities are typical and vary with the utility's standard drawing.