For 96 PCs plus 4 APs, estimate 100 CAT6 drops at 35 m average, giving 3,850 m and 13 boxes. Use 100 faceplates, 5 patch panels, 4 access switches plus 1 PoE switch, and 1 core L3 switch. Assign each lab a /27 subnet from 192.168.10.0/24.
NITC building had 4 research labs each having 24 computers. All labs are located at the 1st floor. Each computer is to be connected in the network from NCR located at 2nd floor. Prepare a bill of quantity (BoQ) with necessary network resources required for complete networking. The BoQ must include estimation of all network resources required.
Assumptions
- 4 labs x 24 computers = 96 computers, all on the 1st floor. The Network Control Room (NCR) is on the 2nd floor, directly above.
- One single-port CAT6 outlet per computer, plus 1 wireless AP per lab (4 drops). Total drops = 96 + 4 = 100.
- Floor height 4 m; horizontal run about 28 m; plus slack: average cable run per drop = 35 m (under the 90 m limit).
- 10% wastage on cable. Cable box = 305 m. Switches are 24-port GE with SFP uplinks. The NCR also needs a router/firewall for the internet link.
Layout
Internet
|
[Router/Firewall] NCR (2nd floor)
|
[Core L3 switch]
|
[Patch panels x5]--[Switch x5 (4 + 1 PoE)]
|
| CAT6 (100 runs, 35 m average)
---+---------+---------+---------+--- 1st floor
Lab 1 Lab 2 Lab 3 Lab 4
24 PC 24 PC 24 PC 24 PC
+ AP + AP + AP + AP
Quantity estimation
- Outlets (single-port faceplate with jack): 96 + 4 = 100.
- Cable length: 100 x 35 = 3,500 m. With 10% wastage = 3,850 m. Boxes = 3,850 / 305 = 12.6, so 13 boxes.
- Patch panel ports = 100. 100 / 24 = 4.2, so 5 patch panels (24-port).
- Switches: 96 PC ports / 24 = 4 switches fully used, plus 1 PoE switch for the 4 APs and spare ports = 5 access switches. One core L3 switch connects them to the router = 1.
- Patch cords: user side 2 m = 100; panel to switch 1 m = 100; switch to core 1 m = 5. Total 205.
- Rack space: 5 panels (5U) + 5 switches (5U) + core (1U) + router/firewall (1U) + cable managers (4U) + UPS (2U) = 18U, so one 24U or 42U rack.
Bill of Quantity
| S.N. | Item | Specification | Qty |
|---|---|---|---|
| 1 | CAT6 UTP cable | 305 m box | 13 boxes |
| 2 | Faceplate + jack | Single-port, CAT6 | 100 |
| 3 | Patch panel | 24-port CAT6 | 5 |
| 4 | Patch cord 2 m | CAT6 | 100 |
| 5 | Patch cord 1 m | CAT6 | 105 |
| 6 | Access switch | 24-port GE + 2 SFP | 4 |
| 7 | PoE switch | 24-port PoE+ | 1 |
| 8 | Core L3 switch | 24-port, SFP+ | 1 |
| 9 | Wireless AP | Dual-band, PoE | 4 |
| 10 | Router / firewall | NAT, DHCP | 1 |
| 11 | Rack | 42U with cable managers | 1 |
| 12 | UPS | 2 kVA | 1 |
| 13 | PVC conduit / trunking | 25 mm | 150 m |
| 14 | Cable ties, labels | lot | |
| 15 | Cable tester | 1 |
IP plan (192.168.10.0/24)
| Network | Subnet | Usable | Gateway |
|---|---|---|---|
| Lab 1 | 192.168.10.0/27 | 30 | .1 |
| Lab 2 | 192.168.10.32/27 | 30 | .33 |
| Lab 3 | 192.168.10.64/27 | 30 | .65 |
| Lab 4 | 192.168.10.96/27 | 30 | .97 |
| Wi-Fi / APs | 192.168.10.128/27 | 30 | .129 |
| Servers / management | 192.168.10.160/27 | 30 | .161 |
Each /27 has 30 usable hosts, enough for 24 PCs and a gateway with spare addresses. The core L3 switch routes between the subnets, and the router provides DHCP (through DHCP relay on the core) and NAT to the internet.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- BOQ for DOECE four computer labs · Internet and Intranet, chapter 5
- BoQ for IOE ICT building six labs · Internet and Intranet, chapter 5
- Prepare AOC, BOQ and summary of cost · Estimating and Costing, chapter 2