- 2075 Baisakh · 6 marks
Estimating sewage quantity for a city
Short answer
Project design population by arithmetic or geometric method. Compute average sewage flow as 0.8×P×q/86400 l/s with q=45-135 lpcd. Apply peak factor 2-3 for max flow, add infiltration (5-10% of DWF) and industrial waste. For combined systems, add storm runoff from rational method with DHM intensity. Example: P=60,000, q=135 lpcd, PF=3 yields Qmax=225 l/s.
Describe the method of estimating the quantity of sewage for a city in Nepal in detail.
The quantity of sewage is estimated from the future population, the water supply per capita, and the factors that raise or reduce the flow. For a city in Nepal (e.g. Pokhara, Biratnagar) the method is as follows.
Step 1: Design population
Collect census data (CBS, Nepal) and project the population for the design period (about 20-25 years after completion) using the arithmetic, geometric or incremental increase method:
- Arithmetic:
- Geometric:
Add floating population (tourists, commuters, students) if large.
Step 2: Water supply rate
Use the design water demand of the city (Nepal Water Supply Corporation/NWSC design guidelines): 45 lpcd for rural and 85-135 lpcd for urban areas, with additions for institutional, commercial and industrial demand and leakage.
Step 3: Average sewage flow
About 80% of supply returns as sewage (the rest is lost in gardening, evaporation, leakage and consumption):
Step 4: Peak and minimum flow
- Peak factor 2 to 3 (higher for small towns); for sewer design.
- Minimum flow about for velocity check at start of the design period.
Step 5: Additions
- Infiltration depending on groundwater table and pipe quality (about 5-10% of DWF in Nepali cities, or 5,000-10,000 l/km/day/cm diameter).
- Industrial wastewater from large industries (from their own records).
- Storm water with if the system is combined or partially separate. The intensity for the Nepal city is taken from the DHM intensity-duration-frequency curves, with .
Step 6: Design discharge
The sewers are designed for at the end of the design period and checked for minimum flow at the beginning (velocity at least 0.6 m/s).
Example
For , lpcd, PF = 3: l/s and l/s.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Sources of sewage and city impact · Sanitary Engineering, chapter 2
- Estimating storm water quantity · Sanitary Engineering, chapter 2 · asked 3×
- Sources and factors of sanitary sewage · Sanitary Engineering, chapter 2 · asked 3×
- Time of critical DO deficit, 50 l/s city · Sanitary Engineering, chapter 6 · asked 2×
- Critical DO deficit, city 100 l/s · Sanitary Engineering, chapter 6 · asked 2×
- Degree of treatment, city 1200 l/s · Sanitary Engineering, chapter 6
- Detail estimate report for sewerage project · Estimating and Costing, chapter 5 · asked 2×
- Components of detail estimate report (road) · Estimating and Costing, chapter 5
- Distribution layout for haphazardly growing city · Water Supply Engineering, chapter 7 · asked 2×
- Compare and contrast pollution in a city · Communication English, chapter 1