Circular sedimentation tank, population 35675

Short answer

One circular tank of 19.5 m diameter, 3.0 m side water depth (total 4.0 m), detention 2.0 h, surface loading 34.8 m³/m²/day.

Design a circular sedimentation tank for a locality having population of 35675. The average water demand is 135 lpcd and 80% of the water consumed converts to sewage. Assume that maximum demand is 2.7 times the average demand. Check surface loading also.

Assumptions: sewage =0.8×135=108=0.8\times 135 = 108 lpcd, so the average flow is 35675×108/1000=3852.935675\times 108/1000 = 3852.9 m³/day; the design flow is the maximum, 2.7×2.7\times average. Detention 2 h at maximum flow, depth 3 m.

Step 1: Design flow

Q=35675×135×0.8×2.7/1000=10402.8 m3/dayQ = 35675\times 135\times 0.8\times 2.7/1000 = 10402.8\ \text{m}^3/\text{day}

Step 2: Capacity

Adopt detention period t=2.0t = 2.0 h and side water depth H=3.0H = 3.0 m (typical for plain sedimentation: 2-3 h, 2.5-4 m).

V=Q t=10402.824×2.0=866.9 m3,A=VH=866.93.0=289.0 m2V = Q\,t = \frac{10402.8}{24}\times 2.0 = 866.9\ \text{m}^3,\qquad A = \frac{V}{H} = \frac{866.9}{3.0} = 289.0\ \text{m}^2

Step 3: Diameter

Provide one circular tank, so A1=AA_1=A.

D=4A1π=4×289.0π=19.18 m ⇒ adopt D=19.5 mD = \sqrt{\frac{4A_1}{\pi}} = \sqrt{\frac{4\times 289.0}{\pi}} = 19.18\ \text{m}\ \Rightarrow\ \text{adopt } D = 19.5\ \text{m}

Adopt a total depth of H+0.5 (free board)+0.5 (sludge zone)=4.0H + 0.5\ (\text{free board}) + 0.5\ (\text{sludge zone}) = 4.0 m, with a central inlet well and a peripheral weir.

Step 4: Checks

Surface loading=Q/NπD2/4=10402.8298.6=34.8 m3/m2/day (usual 25-40 for primary tanks)Weir loading=Q/NπD=10402.8π×19.5=169.8 m3/m/day (should be below about 300)Actual detention=(πD2/4)HQ/N×24=2.07 h\begin{aligned} \text{Surface loading} &= \frac{Q/N}{\pi D^2/4} = \frac{10402.8}{298.6} = 34.8\ \text{m}^3/\text{m}^2\text{/day}\ (\text{usual 25-40 for primary tanks})\\ \text{Weir loading} &= \frac{Q/N}{\pi D} = \frac{10402.8}{\pi\times 19.5} = 169.8\ \text{m}^3/\text{m/day}\ (\text{should be below about 300})\\ \text{Actual detention} &= \frac{(\pi D^2/4)H}{Q/N}\times 24 = 2.07\ \text{h} \end{aligned}

The surface loading lies within the usual range for primary settling (25-40 m³/m²/day), so the tank is satisfactory. The inlet well, scum board and sludge scraper are provided as shown.

   Section (circular, radial flow)
      inlet well        weir/launder
   ->  |__|~~~~~~~~~~~~~~~~~~~~~|_
       |  \                  /  | H = 3.0 m
       |   \______    ______/   | + sludge zone
       +----------\__/----------+
                  sludge hopper -> sludge pipe
        <---------- D = 19.5 m ---------->

Answer: 1 circular sedimentation tank of diameter 19.5 m, side water depth 3.0 m (total depth about 4.0 m), detention 2.0 h, surface loading 34.8 m³/m²/day.