- 2068 Magh (old course) · 10 marks
Septic tank and soak pits, 15 users, Terai
Short answer
Compute volumes: settling 0.675 m³, digestion 0.638 m³, storage 1.700 m³, total 3.01 m³. Tank 2.3 m × 0.9 m × 1.5 m liquid depth + 0.3 m freeboard, two chambers. Soak pit: infiltration area 13.5 m², one circular pit diameter 2.2 m, depth 2.0 m, bottom >1 m above groundwater.
Design a septic tank and numbers of soak pit for 15 numbers of average users. Rate of sewage discharge is 45 lpcd. Cleaning period of septic tank is 4 years interval. Assume other necessary data if required. Location of construction is in Terai area.
Assumptions: Terai has a high ground-water table (about 3 m) and flat land, so soak pits are kept shallow (effective depth 2.0 m) and infiltration rate for sandy soil is taken as 50 L/m²/d; detention 24 h; pit diameter at most 3 m.
Septic tank
- Sewage flow:
- Sewage (settling) zone for 24 h detention:
- Sludge digestion zone:
- Digested sludge storage for 4 years:
Adopt liquid depth m and .
Check: (safe).
Septic tank: internal size (including 0.3 m free board), in two chambers: first chamber m long (2/3), second m (1/3), separated by a partition wall with an opening near mid-depth. Inlet and outlet through T-pipes dipping 0.3 m below water level.
Soak pits
- Required infiltration area: (only the side wall below the inlet is counted; the bottom is ignored as it clogs)
- Adopt effective depth m
Check: .
Soak pit: one circular pit, 2.2 m internal diameter and 2.0 m deep, lined with dry brick/stone masonry with open joints (honeycomb), filled with brick bats/gravel, and covered with a slab.
Because of the high water table, keep the pit bottom at least 1 m above the highest ground-water level; if this cannot be done use dispersion trenches or an evapotranspiration mound instead.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Septic tank and soak pits, hotel of 80 · Sanitary Engineering, chapter 9
- Septic tank and soak pit, 15 users · Sanitary Engineering, chapter 9 · asked 2×
- Septic tank and soak pit, 10 users, 85 l/m²/d · Sanitary Engineering, chapter 9 · asked 2×
- Septic tank and soak pit, hostel of 400 · Sanitary Engineering, chapter 9
- Septic tank and soak pit, household of 80 · Sanitary Engineering, chapter 9 · asked 2×
- Septic tank and soak pit, 8 persons · Sanitary Engineering, chapter 9 · asked 2×
- Domestic water supply; septic tank and soak pit · Building Technology, chapter 12
- Septic tank and soak pit · Building Technology, chapter 12 · asked 7×
- Building services, septic tank and soak pit · Building Technology, chapter 12
- Septic tank with soak pit: excavation, floor, plaster · Estimating and Costing, chapter 6