Sewer diameter for a 12 sq km area

Short answer

Total design discharge 46.78 m³/s. At slope 1/500 the required diameter is 5.343 m (5400 mm) but full velocity 4.20 m/s exceeds scouring limit. Reducing slope to 1/1500 yields acceptable diameter about 6.6 m with velocity 2.77 m/s.

Calculate the diameter of a sewer to serve an area of 12 sq.km with a population density of 250 persons per hectare. The average rate of sewage flow is 235 lpcd. The coefficient of runoff for 50% farthest area is 0.3 and rest of the area is 0.75. Time taken to reach storm water inlet from the farthest point of the catchment is 25 min. Assume storm duration = 20 min and n = 0.013.

The sewer is taken as a combined sewer. Missing data are assumed: slope 1 in 500, peak factor 3, sewer running half full. The 235 lpcd given is already the sewage flow, so no further reduction is applied.

Step 1: Sewage flow

Area = 12 km² = 1200 ha, population =250×1200=300000=250\times1200=300000.

Qsew=300000×235×386400×1000=2.4479 m3/sQ_{sew}=\frac{300000\times235\times3}{86400\times1000}=2.4479\ \text{m}^3/\text{s}

Step 2: Storm water

C=0.5(0.3)+0.5(0.75)=0.525C=0.5(0.3)+0.5(0.75)=0.525. Time of concentration = 25 min; storm duration = 20 min. The intensity for the given 20 min storm is taken from the assumed formula i=760t+10i=\dfrac{760}{t+10} mm/hr:

i=76020+10=25.33 mm/hrQstorm=0.525×25.33×1200360=44.333 m3/s\begin{aligned} i&=\frac{760}{20+10}=25.33\ \text{mm/hr}\\ Q_{storm}&=\frac{0.525\times25.33\times1200}{360}=44.333\ \text{m}^3/\text{s} \end{aligned}

(Because the 20 min storm is shorter than tct_c = 25 min, the farthest part of the area has not yet contributed. Using the full area is on the safe side.)

Step 3: Total discharge

Q=2.4479+44.333=46.781 m3/sQ=2.4479+44.333=46.781\ \text{m}^3/\text{s}

Step 4: Sewer design (S=1/500S=1/500, n=0.013n=0.013, half full)

For d/D=0.5d/D=0.5: θ=2cos⁡−1(1−2d/D)=180.00∘\theta = 2\cos^{-1}(1-2d/D)=180.00^\circ, A/Af=θ−sin⁡θ2π=0.5000A/A_f=\dfrac{\theta-\sin\theta}{2\pi}=0.5000, R/Rf=1−sin⁡θθ=1.0000R/R_f=1-\dfrac{\sin\theta}{\theta}=1.0000, so v/vf=(R/Rf)2/3=1.0000v/v_f=(R/R_f)^{2/3}=1.0000 and Q/Qf=(A/Af)(v/vf)=0.5000Q/Q_f=(A/A_f)(v/v_f)=0.5000 (n taken constant).

Size of the sewer

Discharge when running full:

Qf=QQ/Qf=46.7810.5000=93.562 m3/sQ_f=\frac{Q}{Q/Q_f}=\frac{46.781}{0.5000}=93.562\ \text{m}^3/\text{s}

Manning's formula for a full circular pipe, Qf=0.3117nD8/3S1/2Q_f=\dfrac{0.3117}{n}D^{8/3}S^{1/2}, with S=0.00200S=0.00200 and n=0.013n=0.013:

D=(Qf n0.3117 S1/2)3/8=(93.562×0.0130.3117×0.04472)3/8=5.343 mD=\left(\frac{Q_f\,n}{0.3117\,S^{1/2}}\right)^{3/8}=\left(\frac{93.562\times0.013}{0.3117\times0.04472}\right)^{3/8}=5.343\ \text{m}

Adopt the next standard size, D = 5400 mm.

Check of velocity and capacity

For the adopted pipe: vf=0.3969nD2/3S1/2=4.203v_f=\dfrac{0.3969}{n}D^{2/3}S^{1/2}=4.203 m/s and Qf=96.248Q_f=96.248 m³/s.

v=vf×(v/vf)=4.203×1.0000=4.20 m/sQcapacity=Qf×(Q/Qf)=96.248×0.5000=48.124 m3/s (≥46.781)\begin{aligned} v&=v_f\times(v/v_f)=4.203\times1.0000=4.20\ \text{m/s}\\ Q_{capacity}&=Q_f\times(Q/Q_f)=96.248\times0.5000=48.124\ \text{m}^3/\text{s}\ (\ge 46.781) \end{aligned}

The velocity at maximum flow, 4.20 m/s, is above the maximum non-scouring limit of 3.0 m/s, so this design is not safe against scouring.

Step 5: Revised slope

Since the slope was only assumed, a flatter slope is chosen. With S=1/1500S=1/1500:

D=(93.562×0.0130.3117×0.02582)3/8=6.565 mD=\left(\frac{93.562\times0.013}{0.3117\times0.02582}\right)^{3/8}=6.565\ \text{m}

Adopt D=6.6D=6.6 m. Then vf=2.77v_f=2.77 m/s, and the half-full capacity is 47.4547.45 m³/s (≥46.781\ge 46.781). The velocity of 2.77 m/s lies between 0.6 and 3.0 m/s, so this is satisfactory.

Answer: Design discharge = 46.78 m³/s. At 1 in 500 the required diameter is 5.343 m (5400 mm), but the velocity of 4.20 m/s is too high; at 1 in 1500 provide about 6.6 m diameter (v = 2.77 m/s). For such a large flow, two or more sewers in parallel or a box/arch section would be used in practice.