Skip to main content

Tunnelling methods; shotcreting

Short answer

Methods include drill-and-blast, TBM, NATM, and mechanical excavation. Shotcrete seals the surface, provides immediate flexible support, fills cracks, bonds rock blocks into an arch, and reduces overbreak. Procedure: scale loose rock, wash surface, install mesh or fibres, spray wet-mix or dry-mix concrete in layers holding nozzle 1-1.5 m away at right angles, then cure and test.

Discuss various tunnelling methods used in hydropower projects. What is the purpose of shotcreting? Discuss the procedure.

Tunnelling methods in hydropower projects

  1. Drill and blast: drilling, charging, blasting, ventilation, mucking, scaling and support. It is the method used most in Nepal. Large faces are excavated by top heading and benching.
  2. Tunnel boring machine (TBM): full-face rotary excavation with a segmental lining; fast, and gives a smooth tunnel, but costly, and it needs uniform ground and a long drive.
  3. NATM: excavation with immediate shotcrete, rock bolts and mesh, and monitoring of the deformation, which lets the rock carry part of the load.
  4. Road-headers or hydraulic breakers in soft rock, and cut-and-cover at shallow portals.

Purpose of shotcreting

Shotcrete is concrete sprayed at high speed onto the excavated rock surface.

  • Seals the surface, preventing weathering, slaking and loosening of the joints.
  • Gives immediate support and carries the rock load together with bolts and mesh.
  • Fills the cracks and bonds the rock blocks into a ring (arch action).
  • Smooths the surface and reduces overbreak and hydraulic roughness (as a lining of non-pressure tunnels).
  • Gives quick, flexible support at low cost.

Procedure of shotcreting

  1. Scale the loose rock and wash the surface with an air-water jet to remove dust and loose particles.
  2. Install mesh or add steel/synthetic fibres, and set the thickness gauge pins.
  3. Prepare the mix (cement, aggregate up to 10 mm, admixtures, accelerator) by the dry-mix process (water added at the nozzle) or the wet-mix process (pumped wet concrete).
  4. Spray with the nozzle held 1-1.5 m from the surface and at right angles to it, moving in small circles. Spray from the walls upwards to the crown, in layers of 5-10 cm; apply the second layer after the first has set.
  5. Control the rebound (material that falls away) and remove it; do not reuse it.
  6. Cure the shotcrete by spraying water or a curing compound for several days.
  7. Quality tests: thickness checks, strength tests on cores or panels, and bond tests.

✓ Answer checked by Claude Opus 5.5 (high effort)

All Hydropower Engineering chapter 6 questions →