- 2071 Chaitra · 4+2+2 marks
Tunnelling methods; shotcreting
Short answer
Methods include drill-and-blast, TBM, NATM, and mechanical excavation. Shotcrete seals the surface, provides immediate flexible support, fills cracks, bonds rock blocks into an arch, and reduces overbreak. Procedure: scale loose rock, wash surface, install mesh or fibres, spray wet-mix or dry-mix concrete in layers holding nozzle 1-1.5 m away at right angles, then cure and test.
Discuss various tunnelling methods used in hydropower projects. What is the purpose of shotcreting? Discuss the procedure.
Tunnelling methods in hydropower projects
- Drill and blast: drilling, charging, blasting, ventilation, mucking, scaling and support. It is the method used most in Nepal. Large faces are excavated by top heading and benching.
- Tunnel boring machine (TBM): full-face rotary excavation with a segmental lining; fast, and gives a smooth tunnel, but costly, and it needs uniform ground and a long drive.
- NATM: excavation with immediate shotcrete, rock bolts and mesh, and monitoring of the deformation, which lets the rock carry part of the load.
- Road-headers or hydraulic breakers in soft rock, and cut-and-cover at shallow portals.
Purpose of shotcreting
Shotcrete is concrete sprayed at high speed onto the excavated rock surface.
- Seals the surface, preventing weathering, slaking and loosening of the joints.
- Gives immediate support and carries the rock load together with bolts and mesh.
- Fills the cracks and bonds the rock blocks into a ring (arch action).
- Smooths the surface and reduces overbreak and hydraulic roughness (as a lining of non-pressure tunnels).
- Gives quick, flexible support at low cost.
Procedure of shotcreting
- Scale the loose rock and wash the surface with an air-water jet to remove dust and loose particles.
- Install mesh or add steel/synthetic fibres, and set the thickness gauge pins.
- Prepare the mix (cement, aggregate up to 10 mm, admixtures, accelerator) by the dry-mix process (water added at the nozzle) or the wet-mix process (pumped wet concrete).
- Spray with the nozzle held 1-1.5 m from the surface and at right angles to it, moving in small circles. Spray from the walls upwards to the crown, in layers of 5-10 cm; apply the second layer after the first has set.
- Control the rebound (material that falls away) and remove it; do not reuse it.
- Cure the shotcrete by spraying water or a curing compound for several days.
- Quality tests: thickness checks, strength tests on cores or panels, and bond tests.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Tunnelling methods and supports · Hydropower Engineering, chapter 6
- Forebay design procedure · Hydropower Engineering, chapter 6 · asked 2×
- Advantages and disadvantages of hydropower · Hydropower Engineering, chapter 1 · asked 2×
- Purpose and types of spillways · Hydropower Engineering, chapter 4 · asked 4×
- Licensing provisions in hydropower policy · Hydropower Engineering, chapter 1 · asked 2×
- Draft tube: purpose, setting and efficiency · Hydropower Engineering, chapter 7
- RA: employee-projects with no part used · Database Management System, chapter 3
- RA: projects where all used bolts size 6 · Database Management System, chapter 3
- Equipment used in hydropower construction · Construction Management, chapter 4
- Tunnelling and rock drilling equipment · Construction Management, chapter 4 · asked 3×