Cost of quality

Short answer

Cost of quality (COQ) is the total cost of conformance (prevention and appraisal) plus non-conformance (internal and external failure). The 1-10-100 rule: preventing a defect costs 1 unit, testing finds it for 10, fixing after delivery costs 100; investing in prevention lowers total cost.

What do you mean by cost of quality?

Cost of quality (COQ) is the total cost of all efforts to achieve product or service quality, plus the cost of failing to achieve it. It covers the work to prevent defects, find them and correct them. Juran introduced the cost-of-quality idea, and Philip Crosby, in his book "Quality Is Free", argued that prevention costs less than failure.

Categories

  1. Conformance costs (cost of good quality): money spent to avoid failures.
    • Prevention costs: training, quality planning, process improvement, documentation, better tools, standards.
    • Appraisal costs: inspections, testing, reviews, audits, test equipment.
  2. Non-conformance costs (cost of poor quality): the cost of failures.
    • Internal failure costs: failures found before delivery: rework, scrap, retest, delay.
    • External failure costs: failures found by the customer: warranty, complaints, support, recalls, liability, loss of reputation.
CategoryExamples in a software project
PreventionTraining in secure coding, standards
AppraisalCode reviews, test execution
Internal failureFixing bugs found in QA
External failurePatches after release, customer compensation
Cost
  |  Failure cost  \
  |                 \_____
  |  Prevention + appraisal  /
  +-----------------------------> quality effort

Spending more on prevention and appraisal lowers failure costs and, up to a point, usually gives the lowest total cost.

Use of COQ

  • Cost-benefit analysis in quality planning.
  • Justifying investment in quality improvement.
  • Monitoring trends; a rising failure cost shows a process weakness.
  • Comparing projects.

The 1-10-100 rule

A defect costs 1 unit to prevent, 10 to find and fix in testing and 100 to fix after delivery.

Example: A team spends Rs 50,000 on code reviews (appraisal) and avoids Rs 3 lakh of post-release fixes (external failure).