- 2066 Bhadra (old course) · 4+6 marks
Monitoring and quality, cost, schedule control
Short answer
Monitoring is continuous tracking; evaluation is periodic results assessment; control compares actuals to plan and takes action. Quality control tests materials and work to meet specs; cost control uses earned value to manage budget; schedule control compares progress to baseline, analyzes critical path, and applies crashing or fast-tracking to correct delays.
Define monitoring, evaluation and control. Explain briefly quality control, cost control and schedule control in the project.
Definitions
Project monitoring is the continuous collection, recording and reporting of information on the actual progress of a project (physical work, time, cost, quality, resource use) during implementation, and its comparison with the plan, so that deviations are known.
Project evaluation is the periodic, systematic assessment of a project (during, at the end, or after completion) to judge its relevance, efficiency, effectiveness, impact and sustainability against the objectives, and to draw lessons for decisions and for future projects.
Project control is the process of comparing actual performance with the plan, analysing the variances and taking corrective action (or revising the plan) so that the project is completed within the planned time, cost and quality.
Quality control
Quality control checks that materials and work meet the specifications and standards. This is done through inspection, sampling and testing (cube test, density test), the use of control charts and Pareto/fishbone analysis, and by correcting or rejecting defective work. It is carried out by a quality engineer with a test plan and records.
Cost control
Cost control keeps the actual cost within the approved budget. The budget is set by WBS/cost codes, the actual cost is recorded, the variance is found (actual against budget, or by earned value: CV and CPI), the final cost is forecast (EAC) and corrective action is taken (reduce wastage, improve productivity, control variations and procurement).
Schedule control
Schedule control keeps the work on the planned timetable. Actual progress is compared with the baseline (bar chart, S-curve, SV and SPI); the cause of any delay and its effect on the critical path are found; corrective action is taken (more resources, overtime, re-sequencing, fast-tracking, crashing) and the schedule is updated.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Monitoring vs evaluation; quality control tools · Project Engineering, chapter 4
- Monitoring, evaluation, control; control cycle · Project Engineering, chapter 4 · asked 4×
- Monitoring, evaluation, control must; PMIS · Project Engineering, chapter 4
- Monitoring, evaluation, controlling and life cycle · Project Engineering, chapter 1
- Short note: Monitoring, evaluation, controlling · Project Engineering, chapter 4
- Closed and open control; quality cost · Project Engineering, chapter 4
- TCTO numerical: lowest cost schedule, Rs 400/week · Construction Management, chapter 2
- TCTO numerical: least cost schedule, Rs 2000/week · Construction Management, chapter 2
- How CM helps with delay, quality and cost · Construction Management, chapter 1
- Cost of quality · ICT Project Management, chapter 10