Monitoring, evaluation, control must; PMIS

Short answer

Monitoring tracks progress, control corrects deviations, evaluation judges outcomes; together they ensure accountability and success. A Project Management Information System is an organized system of people, data, and tools that collects, processes, and reports timely information, enabling right decisions and reducing risk of wrong decisions.

Discuss "monitoring, evaluation and control" is a must to succeed in a project. Explain the project management information system and justify "the right information at the right time reduces the risk of wrong decision".

Why monitoring, evaluation and control are a must

A project is a one-time, costly and uncertain job with limited time and money. Plans are made on assumptions, but conditions change during implementation. Without monitoring and control, the project drifts.

  • Monitoring shows the actual progress, cost and quality continuously, so that a delay or overspend is seen early.
  • Control compares the actual with the plan and takes corrective action so that the time, cost and quality targets are achieved.
  • Evaluation judges whether the objectives are being achieved and whether the project is still relevant and efficient, and gives lessons for decisions and future projects.
  • Together they give accountability, avoid waste and loss, reduce risk, satisfy the client and donor, and improve the chance of success.
+--------------+     +------------------+
| 1 Plan:      |     | 2 Implement and  |
| baseline of  |---->| measure actual   |
| time, cost,  |     | progress         |
| quality      |     +--------+---------+
+------^-------+              |
       |                      v
+------+-------+     +------------------+
| 5 Take       |     | 3 Compare actual |
| corrective   |<----| with plan and    |
| action /     |     | find variance    |
| re-plan      |     +--------+---------+
+------^-------+              |
       |                      v
       |             +------------------+
       +-------------| 4 Analyse causes |
                     | and decide       |
                     +------------------+

Project Management Information System (PMIS)

A Project Management Information System (PMIS) is an organised system (manual or computer-based) of people, procedures, data and tools that collects, stores, processes and reports the information project managers need to plan, monitor and control a project. It gives the right information to the right person, at the right time, in the right form.

Components

  • Data input: site reports, measurement books, labour and equipment logs, material receipts, bills, test results, drawings.
  • Database: schedules, budget, cost records, resource and contract data, risk register.
  • Processing tools: spreadsheets, scheduling software (MS Project, Primavera), cost and EVA software.
  • Output reports: progress, variance, cost, resource, quality and exception reports, dashboards.
  • People and procedures: reporting formats, frequency, responsibilities.

Functions

  • Planning and scheduling support; progress and cost tracking.
  • Variance and trend analysis; forecasting of the final cost and completion date.
  • Early warning of problems (exception reporting).
  • Document control and communication among the client, consultant and contractor.
  • Support for decisions, claims and audit.
Site data -> Collect -> Store (database) -> Process
                                              |
Decision <- Reports/Dashboard <- Analyse <----+
   |
   +--> Corrective action --> Site

Benefits

  • Faster and better decisions based on accurate, current data.
  • Better coordination and communication.
  • Early detection of delay and overrun.
  • Less paperwork; reliable records for evaluation and claims.

"The right information at the right time reduces the risk of wrong decisions"

A decision is only as good as the information behind it. If the manager learns of a delay or overspend only after the project is finished, it is too late to correct it. Timely and accurate information from the PMIS means that:

  • a 2-week delay is seen in the weekly report, and extra resources are put on a critical activity while the delay is still small;
  • a cost variance is known at 30 % progress, not at 90 %, so the scope or method can still be changed;
  • the choice between alternatives (for example, overtime or new equipment) is made on facts, not guesses;
  • risk is lowered because uncertain assumptions are replaced by measured data.

On the other hand, late, wrong or excessive information leads to wrong decisions, delay and loss.