- 2067 Asar (old course) · 8 marks
Closed and open control; quality cost
Short answer
Open system has no feedback and does not correct deviations, e.g. a timer pump; closed system measures output and corrects, e.g. thermostat. Quality costs money for prevention and appraisal, but poor quality costs more through rework, claims, and reputation loss. Total quality cost is prevention plus appraisal plus failure costs, and failure costs fall faster as prevention increases.
Explain with examples closed system and open system of control. Justify the statement "Quality costs more, but lack of quality costs even more".
Closed and open system of control
OPEN LOOP CLOSED LOOP
Input -> [Process] -> Out Input -> [Process] -> Out
^ |
+-- [Compare]<------+
(feedback)
| Basis | Open system | Closed system |
|---|---|---|
| Feedback | None | Present |
| Output compared with target | No | Yes |
| Self-correction | No; changes in conditions are not corrected | Yes; deviation is corrected |
| Complexity and cost | Simple, cheap | More complex, needs measurement |
| Accuracy | Low | High |
| Examples | Pump run on a timer; releasing funds monthly without checking progress; a plan carried out blindly | Thermostat of a heater; monthly comparison of actual cost with budget and correction; irrigation gate controlled by water level sensor |
Project control should be a closed system because the environment changes and errors must be corrected.
"Quality costs more, but lack of quality costs even more"
Good quality needs money for prevention (planning, training, procedures) and appraisal (inspection and tests). Poor quality costs far more through failure: rework and rejection (internal failure) and repair, claims and loss of reputation (external failure). For example, testing concrete cubes costs a few hundred rupees, but a defective slab may cost lakhs to demolish and recast.
As spending on prevention and appraisal increases, the failure cost falls faster, so the total cost goes down to an optimum. Hence lack of quality is more costly than quality.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Quality costs more, lack costs even more · Project Engineering, chapter 4 · asked 2×
- Traffic light system of Kathmandu: open or closed loop · Control Systems, chapter 1