Quality costs more, lack costs even more
Short answer
Quality is fitness for use or conformance to requirements. Quality costs more due to prevention and appraisal spending, but lack of quality incurs even higher internal and external failure costs like rework, repairs, and loss of goodwill. As prevention/appraisal increase, total quality cost falls to an optimum, proving that failure costs outweigh the cost of achieving quality.
Define quality. Justify the statement "quality costs more but lack of quality costs even more", explaining the total quality cost included to achieve good quality.
Quality
Quality is the degree to which the project deliverable satisfies the specified requirements and the needs of the client; in simple words, "fitness for use" or "conformance to requirements".
Quality costs more, but lack of quality costs even more
Good quality needs money for planning, training, better materials, inspection and testing. But poor quality is far more expensive: rework, rejection, delay, repair, claims, loss of goodwill and, in construction, structural failure and loss of life. The total cost of quality is:
| Cost | Examples |
|---|---|
| Prevention | Quality plan, training, procedures, skilled supervision |
| Appraisal | Inspection, material and lab tests, audits |
| Internal failure | Rework of faulty concrete, scrap, re-testing, delay |
| External failure | Repair after handover, warranty, compensation, legal costs |
Illustration (Rs thousand, for one slab-casting package):
| Spending on prevention and appraisal | Failure cost (rework, repair) | Total cost of quality |
|---|---|---|
| 10 | 80 | 90 |
| 20 | 40 | 60 |
| 30 | 20 | 50 |
| 40 | 15 | 55 |
As spending on prevention and appraisal increases, the failure cost at first falls much faster, so the total cost falls until it reaches an optimum (Rs 50 thousand here); beyond that point, extra spending saves less than it costs. For example, spending Rs 20,000 on testing and supervision of a slab can avoid demolition and recasting costing lakhs. Hence the statement is justified: the cost of a lack of quality (failure costs) is greater than the cost of achieving quality.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Closed and open control; quality cost · Project Engineering, chapter 4
- QA vs QC; types of cost of quality · Project Engineering, chapter 4 · asked 2×
- Monitoring and quality, cost, schedule control · Project Engineering, chapter 4
- Quality; cost of quality; assuring quality · Project Engineering, chapter 4
- Justify higher voltage/more circuits for more power · Transmission and Distribution System Design, chapter 2
- Break-even cost comparison of three sites · Industrial Engineering and Management, chapter 2
- Total quality management · ICT Project Management, chapter 10
- How CM helps with delay, quality and cost · Construction Management, chapter 1