Quality is fitness for use or conformance to requirements. Quality costs more due to prevention and appraisal spending, but lack of quality incurs even higher internal and external failure costs like rework, repairs, and loss of goodwill. As prevention/appraisal increase, total quality cost falls to an optimum, proving that failure costs outweigh the cost of achieving quality.

Define quality. Justify the statement "quality costs more but lack of quality costs even more", explaining the total quality cost included to achieve good quality.

Quality

Quality is the degree to which the project deliverable satisfies the specified requirements and the needs of the client; in simple words, "fitness for use" or "conformance to requirements".

Quality costs more, but lack of quality costs even more

Good quality needs money for planning, training, better materials, inspection and testing. But poor quality is far more expensive: rework, rejection, delay, repair, claims, loss of goodwill and, in construction, structural failure and loss of life. The total cost of quality is:

Total quality cost=Prevention+Appraisal+Internal failure+External failure\text{Total quality cost} = \text{Prevention} + \text{Appraisal} + \text{Internal failure} + \text{External failure}
CostExamples
PreventionQuality plan, training, procedures, skilled supervision
AppraisalInspection, material and lab tests, audits
Internal failureRework of faulty concrete, scrap, re-testing, delay
External failureRepair after handover, warranty, compensation, legal costs

Illustration (Rs thousand, for one slab-casting package):

Spending on prevention and appraisalFailure cost (rework, repair)Total cost of quality
108090
204060
302050
401555

As spending on prevention and appraisal increases, the failure cost at first falls much faster, so the total cost falls until it reaches an optimum (Rs 50 thousand here); beyond that point, extra spending saves less than it costs. For example, spending Rs 20,000 on testing and supervision of a slab can avoid demolition and recasting costing lakhs. Hence the statement is justified: the cost of a lack of quality (failure costs) is greater than the cost of achieving quality.