System view of project management
Short answer
The systems view of project management treats the project as part of a larger organisation. Its three parts are systems philosophy (thinking of things as systems), systems analysis (problem-solving by defining scope and evaluating alternatives), and systems management (addressing business, technological and organisational issues).
What do you mean by project management system? Explain with 3 parts (3 essences) of the project's system view of project management.
A project management system is the organised set of processes, people, tools and methods through which a project is managed. The systems view of project management (Schwalbe) means treating the project as part of a larger organisation and looking at all its interrelated parts, rather than viewing it in isolation. It is based on the systems approach: a holistic, analytical and problem-solving approach with three parts.
The three parts of the systems view
- Systems philosophy
- A model for thinking of things as systems, i.e. sets of interacting components working within an environment to fulfil some purpose.
- The project is seen as part of the organisation, and decisions are made considering their effect on the whole organisation.
- Systems analysis
- A problem-solving approach that requires defining the scope of the system, dividing it into components, and then identifying and evaluating its problems, opportunities, constraints and needs.
- The analyst then examines alternative solutions and recommends the best one.
- Systems management
- Addresses the business, technological and organisational issues before making changes to a system.
- Considers not only technology but also the people, politics and finances of the organisation.
Systems approach
/ | \
Philosophy Analysis Management
(think as (solve (business, tech,
system) problem) organisation)
Application to projects
- Project managers must see how a project interacts with other projects, departments and stakeholders.
- They must analyse the project's problems step by step (WBS, risk analysis).
- They must consider organisational and technological issues, e.g. whether the new ERP matches the work culture.
Example: Introducing new billing software in a hospital also affects finance staff, patients, training and existing databases. Systems thinking helps to plan all of these together.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Types of project system view · ICT Project Management, chapter 5
- Project management information system · ICT Project Management, chapter 7
- Project management body of knowledge · ICT Project Management, chapter 2
- General management skills and project management · ICT Project Management, chapter 2
- Project portfolio management · ICT Project Management, chapter 3
- Define project management · ICT Project Management, chapter 4
- Event management system summary and class diagram · Object Oriented Analysis and Design, chapter 2
- Function of project management in Nepal · Construction Management, chapter 1
- Types of projects; effect of project management · Project Engineering, chapter 1
- Project vs traditional management; external environment · Project Engineering, chapter 1