Project characteristics versus permanent systems

Short answer

A project is temporary with a unique output and a team disbanded after completion, while a permanent system operates continuously with routine work and permanent staff. Projects have high uncertainty and detailed planning, whereas permanent systems use standard procedures.

Discuss, citing project characteristics, how a project can be differentiated from other permanent systems.

A project is a temporary system for a unique result, whereas a permanent system (for example a hospital, a factory in operation, an electricity utility) keeps running to give continuous output.

BasisProjectPermanent system
LifeTemporary, definite start and endContinuous, no fixed end
ObjectiveSpecific, one-time deliverableOngoing operation and routine output
WorkUnique, non-repetitiveRepetitive, routine
TeamTemporary, disbanded at completionPermanent staff
OrganisationOften a matrix or project teamFunctional hierarchy
UncertaintyHigh, new situation each timeLow, established procedure
PlanningDetailed plan for each projectStandard procedures and policies
ControlTime, cost and quality against the planEfficiency and output standards
ExampleConstruction of a 50 bed hospitalDaily running of the hospital

When the project is complete, the product is handed over to the permanent system for operation. A project is therefore recognised by its definite objective, limited time, unique nature, temporary team and constrained resources.