Skip to main content

Project, characteristics, stages of estimate

Short answer

A project is a temporary, unique undertaking with a definite objective, limited resources, risk and a life cycle. Estimating stages are identification/preliminary estimate, survey, planning/design, taking out quantities, rate analysis, detailed estimate with contingency and VAT, report/approval, and tendering/revision.

What is project? Explain its characteristics. Describe the stages of estimating a project.

Project

A project is a one-time, temporary undertaking carried out by a team with limited resources to create a unique product, service or facility (for example a road, bridge, building or water supply scheme).

Characteristics of a project

  1. Definite objective: it is done to achieve a clear goal.
  2. Unique: each project differs in location, design and conditions.
  3. Temporary: it has a start date and an end date.
  4. Limited resources: budget, labour, materials, equipment and time are fixed.
  5. Complexity: several disciplines and organisations (owner, designer, contractor, consultant) work together.
  6. Risk and uncertainty: weather, geology, price change and delay affect it.
  7. Life cycle: it passes through conception, planning, execution and closing.

Stages of estimating a project

StageWork done
1. Identification and preliminary estimateIdea, need, rough cost from cost per unit (per km, per m², per family) to check feasibility
2. Survey and investigationTopographic, geological, hydrological, traffic and soil surveys
3. Planning and designLayout, structural and service design, drawings, specifications
4. Taking out quantitiesMeasurement of each item from drawings, abstracting them in a BOQ
5. Rate analysisRates from norms and District Rates, with lead and lift, transport, overhead and profit
6. Detailed estimateQuantity × rate for each item; abstract of cost with contingency, supervision and VAT
7. Estimate report and approvalReport with drawings, specifications, rate analysis; technical and financial approval
8. Tendering and revisionBid document is prepared; revised or supplementary estimates are made if the scope changes

✓ Answer checked by Claude Opus 5.5 (high effort)

All Estimating and Costing chapter 5 questions →