Stages of project estimate

Short answer

Estimate stages progress from preliminary approximate cost to detailed accuracy: identification, survey and investigation, design and drawings, quantity calculation, rate analysis, detailed estimate and abstract of cost, report preparation, then approval and tendering. Revised or supplementary estimates cover later changes.

Describe the different stages of project estimate.

A project estimate is prepared in steps, each making the cost more accurate than the last.

  1. Identification (preliminary/approximate estimate): the need for the project is established and a rough cost is obtained from the plinth-area rate, cost per km, or the cost of a similar project. This is used for the feasibility decision and budget allocation.
  2. Survey and investigation: topography, soil, geology, hydrology and traffic data are collected to decide the layout.
  3. Design and drawings: the project is designed, and detailed drawings and specifications are prepared.
  4. Quantity calculation: the quantity of each item is measured from the drawings and entered in a bill of quantities.
  5. Rate analysis: the rates of items are fixed from norms, material and labour rates, lead and lift, transport, overhead and profit.
  6. Detailed estimate and abstract of cost: the cost of each item is calculated and the costs are added; contingency, supervision, escalation and VAT are included.
  7. Preparation of the report: the estimate report with drawings, specifications, calculations and rate analysis is written.
  8. Approval and tendering: the competent authority approves the estimate, and it becomes the basis for tender evaluation. Later, revised or supplementary estimates cover changes during construction.