Tasks in preparing building project estimate
Short answer
Estimator studies drawings/specs/site and includes preliminary site works, substructure, superstructure, finishes, roofing, services, external works, rates and taxes, BOQ and abstract. Also include seismic/NBC requirements, approval fees, municipal requirements, overhead, profit, VAT 13%, contingencies and supervision.
What are the works/tasks that an estimator has to take into account in preparing the estimate of a building project? Explain in brief.
An estimator turns drawings and specifications into a complete cost by taking into account every work that is needed to complete and hand over the building, not only the visible main work.
Works and tasks to be considered
- Study of drawings, specifications and site: read plans, sections, structural and service drawings; visit the site for access, soil, water and power.
- Preliminary and site works: site clearance, setting out, temporary shed and store, fencing, water and electricity for construction, soil test.
- Substructure: excavation, PCC, foundation (footing, plinth beam), masonry in substructure, DPC, backfilling, plinth filling.
- Superstructure: columns, beams, slabs, brick or block walls, lintels, staircases, parapet, formwork and reinforcement.
- Finishing works: plaster, flooring, tiles, skirting, doors and windows, painting, whitewash, ceilings, railings.
- Roofing: truss or slab, CGI sheet, waterproofing, rain-water pipes.
- Services: sanitary and plumbing, drainage and septic tank, water tank, electrical wiring, fittings, earthing, fire safety, lift (if provided).
- External works: boundary wall, gate, paving, drains, landscaping.
- Rates and taxes: rate analysis from District Rates, overhead and profit, VAT 13%, insurance, contingencies (usually 5%), supervision charges, price adjustment.
- Bill of quantities and abstract: measure each item, group them into a BOQ, and prepare the abstract of cost.
Items such as seismic details (NBC 105, NBC 201/202), approval fees and the municipality's requirements are also included.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Preparing a detailed estimate of a building · Estimating and Costing, chapter 2 · asked 4×
- Requisites of project estimate; factors · Estimating and Costing, chapter 5
- Detail estimate report for sewerage project · Estimating and Costing, chapter 5 · asked 2×
- Procedure of preliminary estimate (office building) · Estimating and Costing, chapter 3 · asked 2×
- What is project? How is building project estimated · Estimating and Costing, chapter 5
- Define project; irrigation project estimate · Estimating and Costing, chapter 5 · asked 4×
- IOE entrance scores: estimator and consistency · Probability and Statistics, chapter 6
- Typical job layout of a building project · Construction Management, chapter 6 · asked 4×
- CPM network, building project (A to K) · Project Engineering, chapter 3
- Preparing cement mortar by manual process · Building Technology, chapter 3 · asked 2×