- Asked 4/22
- 2074 Asoj · 6 marks
- 2073 Shrawan
- 2068 Baisakh (old course) · 4 marks
- 2082 Bhadra · 2 marks
Preparing a detailed estimate of a building
Short answer
Study the drawings and specifications, then list items in construction order. Take out quantities using the long wall-short wall or centre line method on dimension sheets. Abstract quantities into a bill of quantities, adopt or analyse rates, and compute cost (quantity × rate). Add contingency (3–5%) and VAT (13%) to get the total estimated cost, and prepare a report.
Describe how you will prepare a detailed estimate of a building.
A detailed estimate is prepared by dividing the building into items of work, taking out the quantities of each item from the drawings, and applying rates. The steps are:
- Study the drawings and specifications: plan, section, elevation, foundation and structural drawings, and door/window schedules.
- List the items in the order of construction: earthwork, PCC, foundation masonry/RCC, DPC, superstructure masonry, columns, beams, slab, doors and windows, plastering, flooring, painting, roofing, sanitary and electrical works.
- Take out quantities of each item using the long wall-short wall or centre line method. Use the dimension columns: number x length x breadth x height, and make deductions for openings. A quantity sheet looks like this:
| Item | No. | L | B | H | Quantity |
|---|
- Abstract the quantities (collect similar items) in a bill of quantities.
- Rate analysis: adopt rates from the District Rate or analyse them using DUDBC norms and local rates.
- Abstract of cost: quantity x rate for each item gives the amount; sum of all items is the base cost.
- Add provisions: contingency (3 to 5%), work-charged establishment/supervision, and VAT (13%) to get the total estimated cost.
- Prepare the report: a brief report with the specifications, assumptions, drawings, and the cost summary.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Tasks in preparing building project estimate · Estimating and Costing, chapter 5 · asked 2×
- Principle of units; data for detailed estimate · Estimating and Costing, chapter 1
- Procedure of preliminary estimate (office building) · Estimating and Costing, chapter 3 · asked 2×
- Data required for detailed estimate · Estimating and Costing, chapter 1
- Requisites of project estimate; factors · Estimating and Costing, chapter 5
- Preliminary estimate: 4-storied office, 2000 m² · Estimating and Costing, chapter 3 · asked 2×
- Preparing cement mortar by manual process · Building Technology, chapter 3 · asked 2×
- Contractor asks supervisor to prepare running bill · Engineering Professional Practice, chapter 7
- Prepare tender notice for commercial complex · Construction Management, chapter 5
- Procedure to prepare bills · Construction Management, chapter 8 · asked 3×