- 2081 Bhadra · 3 marks
Data required for detailed estimate
Short answer
A detailed estimate needs complete drawings, specifications of materials and workmanship, rates from District Rates and DUDBC norms with rate analysis, item-wise quantities, site data, provisions for contingency and taxes, and contract conditions.
List out the data required for the detailed estimate of any construction project.
The data required for a detailed estimate are:
- Drawings: plans, elevations, sections, foundation and structural details, and door, window and finishing schedules, with dimensions.
- Specifications: the quality and standard of materials and workmanship of each item (mix proportions, grade of concrete and steel, brick class, finish).
- Rates: District Rates, the DUDBC norms (consumption of materials and labour per unit of work), and the rate analysis of each item, including transport (lead) and overhead.
- Quantities: item-wise measurements, taken out by a standard method (long wall-short wall or centre line) with units as per IS 1200 / Nepal practice.
- Site information: soil condition, water table, location of material sources and lead, availability of labour and water.
- Provisions and taxes: contingency, work-charged establishment, VAT (13%), and price adjustment as applicable.
- Time and contract conditions: the construction period and the conditions that affect the cost.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Principle of units; data for detailed estimate · Estimating and Costing, chapter 1
- Define project; irrigation project estimate · Estimating and Costing, chapter 5 · asked 4×
- Detail estimate report for sewerage project · Estimating and Costing, chapter 5 · asked 2×
- Preparing a detailed estimate of a building · Estimating and Costing, chapter 2 · asked 4×
- Estimating, purpose and data required · Estimating and Costing, chapter 1 · asked 6×
- Data required for rate analysis (building) · Estimating and Costing, chapter 4
- Define reserve and estimate construction material · Engineering Geology II, chapter 7 · asked 10×
- Characteristics of a construction project · Construction Management, chapter 1
- Internal risk of Nepalese construction project · Project Engineering, chapter 5
- Final location and detailed survey · Transportation Engineering I, chapter 2 · asked 3×