Define project; irrigation project estimate

Short answer

A project is a temporary one-time undertaking with defined objective, scope, budget, schedule, and end. Irrigation estimate needs survey, hydrology, geology/soil, designs, quantities, rates, land/social data, specs and time. Report sub-heads: preliminary, land/compensation, headworks, canals, canal structures, drainage, buildings/roads, electro-mechanical, environmental/social, tools/plant, supervision and contingencies.

Define project. Discuss the estimate of an irrigation project (data required and sub-heads to be included in the detailed estimation report).

Project

A project is a temporary, one-time undertaking with a defined objective, scope, budget, schedule and a clear start and end, carried out to create a unique product or facility. An irrigation project, for example, aims to bring water to a command area through a diversion weir, canals and structures.

Data required for an irrigation project estimate

  1. Topographic and survey data: contour map, longitudinal profile and cross-sections of canal alignment, command area map.
  2. Hydrological data: river discharge records, flood levels, rainfall, water requirement of crops (duty/delta).
  3. Geological and soil data: bed material at weir site, soil type along canal, seepage, bearing capacity.
  4. Design drawings: layout plan, weir and canal designs, drawings of all structures.
  5. Quantities: earthwork, concrete, masonry, gabion, steel, etc., from the drawings.
  6. Rates: District Rates, rate analysis and norms of DUDBC/Department of Irrigation, lead and lift for materials, transport, taxes.
  7. Land and social data: land to be acquired, compensation, crops, forest and environmental clearance, resettlement.
  8. Specifications and time: construction method, season, work programme.

Sub-heads of the detailed estimation report

Sub-headMain items
A. PreliminarySurvey, investigation, design, feasibility study, soil tests
B. Land and compensationLand acquisition, trees, structures, forest clearance
C. Head worksDiversion weir/barrage, intake, under-sluice, settling basin, river training
D. CanalsMain, branch and distributary canals: earthwork, lining
E. Canal structuresRegulators, aqueducts/siphons, drops, culverts, escapes, outlets, bridges
F. DrainageField and main drains, flood protection
G. Buildings and roadsInspection path, canal roads, office/quarters, gauge posts
H. Electro-mechanicalGates, hoists, pump (if any)
I. Environmental and socialMitigation, afforestation, user training
J. Tools and plant, miscellaneousEquipment, communications
K. Establishment/supervision and contingenciesSupervision ~3–5%, physical contingency ~5%, price escalation, VAT 13%

The report contains an introduction, abstract of cost, detailed estimate sheets, rate analysis, specifications, drawings and a construction programme.