Sub-heads of items of work (building)

Short answer

The sub-heads are: site preparation and earthwork; plain concrete work; foundation and masonry; reinforced concrete work; doors, windows and woodwork; roofing; flooring; plastering and pointing; finishing; water supply and sanitary works; electrical works; and miscellaneous and external works. Contingency, VAT, and work-charged establishment are added to the total of all sub-heads.

What are the sub-heads of various items of work for a building project?

A building estimate is divided into sub-heads (groups of similar items), arranged in the order of construction. This makes quantity taking and checking easy.

SNSub-headTypical items
1Site preparation and earthworkSite clearance, setting out, excavation, backfilling, disposal
2Concrete work (plain)PCC in foundation, brick/stone soling, DPC
3Foundation and masonryBrick/stone masonry in foundation, plinth, superstructure, partition walls
4Reinforced concrete workConcrete in footings, columns, beams, slabs, stairs, lintels; formwork; reinforcement
5Doors, windows and woodworkFrames, shutters, ventilators, hardware, grills
6RoofingRoof truss, CGI/tile roofing, waterproofing, parapet
7FlooringFloor base, tiles/terrazzo/cement punning, skirting, dado
8Plastering and pointingInternal and external plaster, pointing
9FinishingWhitewash, distemper, painting of doors, windows, walls
10Water supply and sanitary worksPipes, fittings, W.C., basin, septic tank, drainage
11Electrical worksWiring, fixtures, switches, earthing
12Miscellaneous and external worksBoundary wall, gate, drain, paving, landscaping, lightning conductor

Finally, contingency, VAT and work-charged establishment are added to the total of all sub-heads.