CPM network, building project (A to K)

Short answer

The building project completes in 33 weeks. Critical path: A–D–I. The critical path represents the minimum project duration; activities on it have zero total float and any delay extends the project.

Draw a network diagram and find out EST, EFT, LST, LFT, TF, FF, independent float, interfering float and the project completion time of a building project having the following details. What is the significance of critical path in the network analysis?

ActivityImmediate PredecessorDuration (weeks)
A-10
B-12
C-9
DA8
EA5
FB13
GC6
HC4
ID15
JE, F, G7
KH9

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (weeks). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.

(1) --A(10)--> (2)
(1) --B(12)--> (3)
(1) --C(9)--> (4)
(2) --D(8)--> (5)
(2) --E(5)--> (6)
(3) --F(13)--> (6)
(4) --G(6)--> (6)
(4) --H(4)--> (7)
(5) --I(15)--> (8)
(6) --J(7)--> (8)
(7) --K(9)--> (8)

The network has 8 events and no dummy activities. The start event is (1) and the end event is (8).

Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

  • A: EST = 0; EFT = 0 + 10 = 10
  • B: EST = 0; EFT = 0 + 12 = 12
  • C: EST = 0; EFT = 0 + 9 = 9
  • G: EST = EFT of C = 9; EFT = 9 + 6 = 15
  • H: EST = EFT of C = 9; EFT = 9 + 4 = 13
  • D: EST = EFT of A = 10; EFT = 10 + 8 = 18
  • E: EST = EFT of A = 10; EFT = 10 + 5 = 15
  • F: EST = EFT of B = 12; EFT = 12 + 13 = 25
  • K: EST = EFT of H = 13; EFT = 13 + 9 = 22
  • I: EST = EFT of D = 18; EFT = 18 + 15 = 33
  • J: EST = max(E:15, F:25, G:15) = 25; EFT = 25 + 7 = 32

Project duration = largest EFT = 33 weeks.

Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

  • J: LFT = project duration = 33; LST = 33 - 7 = 26
  • I: LFT = project duration = 33; LST = 33 - 15 = 18
  • K: LFT = project duration = 33; LST = 33 - 9 = 24
  • F: LFT = LST of J = 26; LST = 26 - 13 = 13
  • E: LFT = LST of J = 26; LST = 26 - 5 = 21
  • D: LFT = LST of I = 18; LST = 18 - 8 = 10
  • H: LFT = LST of K = 24; LST = 24 - 4 = 20
  • G: LFT = LST of J = 26; LST = 26 - 6 = 20
  • C: LFT = min(G:20, H:20) = 20; LST = 20 - 9 = 11
  • B: LFT = LST of F = 13; LST = 13 - 12 = 1
  • A: LFT = min(D:10, E:21) = 10; LST = 10 - 10 = 0

Floats

  • Total float TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT
  • Free float FF=min⁡(EST of successors)−EFTFF = \min(\text{EST of successors}) - EFT
  • Interfering float IntF=TF−FFIntF = TF - FF
  • Independent float IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)

Result table

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A100100100000
B120121131010
C9091120110110
D8101810180000
E5101521261110110
F13122513261010
G69152026111010
H49132024110110
I15183318330000
J7253226331100
K913222433111100

Event times (TE from the forward pass, TL from the backward pass):

EventTE (earliest)TL (latest)Slack
1000
210100
312131
492011
518180
625261
7132411
833330

Critical path and project duration

  • Critical activities (TF = 0): A, D, I
  • Critical path: A - D - I (= 10+8+15 = 33 weeks)

Answer: the building project is completed in 33 weeks; critical path = A - D - I

Significance of the critical path

  • It gives the minimum time in which the project can be completed (33 weeks here).
  • Critical activities (A, D, I) have zero float; a delay in any of them delays the building by the same time, so they need close supervision and first priority for labour, material and equipment.
  • To shorten the project (crashing), only critical activities need to be speeded up; shortening non-critical activities wastes money.
  • Non-critical activities (e.g. B, F, H, K) have float and can be rescheduled to level the resources.
  • It is the basis for monitoring and updating the schedule; the critical path can change when non-critical activities use up their float.