- Practice · 8 marks
PERT expected time and completion probability
Short answer
Critical path is B-D-F-G with expected project duration 22 weeks and standard deviation 2.71 weeks. Probability of completion within 24 weeks is 77% (Z=0.74). Probability within 20 weeks is 23% (Z=-0.74).
A project has the activities below with optimistic (a), most likely (m) and pessimistic (b) times in weeks:
| Activity | a | m | b | Predecessors |
|---|---|---|---|---|
| A | 2 | 4 | 6 | - |
| B | 3 | 5 | 13 | - |
| C | 4 | 6 | 8 | A |
| D | 5 | 8 | 17 | A, B |
| E | 2 | 3 | 4 | C |
| F | 3 | 5 | 7 | D |
| G | 1 | 2 | 3 | E, F |
(a) Calculate the expected time and variance of each activity. (b) Find the critical path and expected project duration. (c) Find the probability that the project is completed within 24 weeks and within 20 weeks.
(a) Expected time and variance
PERT uses the beta distribution:
| Act. | ES | EF | LS | LF | Float | ||
|---|---|---|---|---|---|---|---|
| A | (2+16+6)/6 = 4 | 0.444 | 0 | 4 | 2 | 6 | 2 |
| B | (3+20+13)/6 = 6 | 2.778 | 0 | 6 | 0 | 6 | 0 |
| C | (4+24+8)/6 = 6 | 0.444 | 4 | 10 | 11 | 17 | 7 |
| D | (5+32+17)/6 = 9 | 4.000 | 6 | 15 | 6 | 15 | 0 |
| E | (2+12+4)/6 = 3 | 0.111 | 10 | 13 | 17 | 20 | 7 |
| F | (3+20+7)/6 = 5 | 0.444 | 15 | 20 | 15 | 20 | 0 |
| G | (1+8+3)/6 = 2 | 0.111 | 20 | 22 | 20 | 22 | 0 |
(b) Critical path
Zero-float activities: B, D, F, G. Expected project duration weeks.
(c) Probability
Variance of the project = sum of variances on the critical path only:
- For 24 weeks: , so (from the standard normal table).
- For 20 weeks: , so .
Answer: Critical path B-D-F-G, expected duration 22 weeks, sigma = 2.71 weeks; P(finish within 24 weeks) = 77%; P(within 20 weeks) = 23%.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3
- Difference between CPM and PERT · Industrial Engineering and Management, chapter 3
- Expected time of contractors (PERT) · Project Engineering, chapter 3
- Dummy activity; use of critical path in CPM · Project Engineering, chapter 3
- Critical path and dummy activity significance · Project Engineering, chapter 3
- Bar chart; expected time and variance · Project Engineering, chapter 3
All Industrial Engineering and Management chapter 3 questions →