- 2065 Shrawan (old course) · 8 marks
Bar chart; expected time and variance
Short answer
A bar chart shows activities as horizontal bars on a time scale; it is simple and shows start, finish and overlap, but not logical dependence, critical path or float. For to=6, tm=8, tp=12, te=(6+4*8+12)/6=8.33 time units and variance=((12-6)/6)^2=1.
Draw a bar chart and explain its advantages and disadvantages. Also find te and variance when to, tm and tp are 6, 8, 12.
Bar chart
A bar chart shows each activity as a horizontal bar on a time scale; the length of the bar is the duration. Example: house project (weeks).
0 4 8 12 16 20 24 (wk)
+------------------------
A Site clearing |#
B Excavation | ##
C Foundation | ###
D Plinth beam | ##
E Walls+columns | #####
F Roof slab | ###
G Plumb/electric| ###
H Plastering | ###
I Floor,doors | ###
J Painting | ##
+------------------------
Advantages
- Simple to prepare, read and understand, even for non-technical persons.
- Shows start, finish, duration and overlap of activities on a time scale.
- Cheap and quick; needs no special training.
- Good for presenting the summary to top management and site staff.
- Progress can be marked on the bars and compared with the plan.
- Useful for resource scheduling on a time scale.
Disadvantages
- Does not show the logical dependence between activities, so the effect of a delay on other activities is not seen.
- Critical activities and float are not shown, so the manager cannot say where attention is needed.
- Not suitable for large and complex projects; the chart becomes crowded.
- Difficult to update; any change in logic needs redrawing.
- Durations are single-point values; uncertainty is not considered.
- Does not show resource or cost relations.
Expected time and variance (PERT)
Given: optimistic time , most likely time , pessimistic time .
Answer: and variance (standard deviation 1).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM vs PERT; te and variance for x, y · Project Engineering, chapter 3
- Expected time of contractors (PERT) · Project Engineering, chapter 3
- Network errors; expected time of engineers · Project Engineering, chapter 3
- Bar chart advantages and limitations · Project Engineering, chapter 3 · asked 2×
- Planning in dynamic environment; linked bar chart · Project Engineering, chapter 3
- Planning, scheduling; linked bar chart · Project Engineering, chapter 3
- Short note: TE and TM modes · Electromagnetism, chapter 6 · asked 2×
- TE vs TM mode in circular waveguide · RF and Microwave Engineering, chapter 4
- PERT expected time and completion probability · Industrial Engineering and Management, chapter 3
- Bar chart vs CPM/PERT as planning tool · Construction Management, chapter 2 · asked 3×