Expected time of contractors (PERT)

Short answer

Using te = (t_o+4t_m+t_p)/6 and σ = (t_p–t_o)/6. Contractor A: te = 7.67, σ = 1.33; B: te = 10.33, σ = 1.00; C: te = 5.00, σ = 0.67. Contractor C is preferred because it has the shortest expected time and smallest standard deviation, making it the fastest and most certain.

Find out the expected time of each contractor to complete a given project having the following details. Also find out which contractor you prefer for operation and why?

Contractortotmtp
A5713
B61112
C357

Expected time te=to+4tm+tp6t_e = \dfrac{t_o + 4t_m + t_p}{6}; standard deviation σ=tp−to6\sigma = \dfrac{t_p - t_o}{6} (the unit of time is as given).

Contractor A (5,7,135, 7, 13): te=5+28+136=466=7.67t_e = \dfrac{5 + 28 + 13}{6} = \dfrac{46}{6} = 7.67, σ=13−56=1.33\sigma = \dfrac{13 - 5}{6} = 1.33, variance =1.78= 1.78

Contractor B (6,11,126, 11, 12): te=6+44+126=626=10.33t_e = \dfrac{6 + 44 + 12}{6} = \dfrac{62}{6} = 10.33, σ=12−66=1.00\sigma = \dfrac{12 - 6}{6} = 1.00, variance =1.00= 1.00

Contractor C (3,5,73, 5, 7): te=3+20+76=306=5.00t_e = \dfrac{3 + 20 + 7}{6} = \dfrac{30}{6} = 5.00, σ=7−36=0.67\sigma = \dfrac{7 - 3}{6} = 0.67, variance =0.44= 0.44

Contractortot_otmt_mtpt_ptet_eσ\sigmaVariance
A57137.671.331.78
B6111210.331.001.00
C3575.000.670.44

Choice of contractor

Contractor C is preferred because:

  • it has the shortest expected time (5.00 against 7.67 and 10.33);
  • it also has the smallest standard deviation (0.67) and variance (0.44), so its completion time is the most certain, and the risk of delay is the least.

(Cost and quality are assumed equal; if they differ, they must be considered along with time.)

Answer: tet_e = 7.67 (A), 10.33 (B), 5.00 (C); choose contractor C.