CPM vs PERT; te and variance for x, y

Short answer

CPM uses deterministic single time, while PERT uses three probabilistic times. te = (t_o+4t_m+t_p)/6, σ = (t_p–t_o)/6. For x: te = 6.00, σ = 0.67, variance = 0.44; for y: te = 4.83, σ = 0.50, variance = 0.25. y is more certain because of smaller SD and variance.

What are the differences between CPM and PERT? Find the te (time estimates) for x and y where to, tm, tp are 4, 6, 8 for x and 3, 5, 6 for y. Also find which is more certain by using S.D. and variance.

Difference between CPM and PERT

BasisCPMPERT
Time estimateOne (deterministic)Three: to,tm,tpt_o, t_m, t_p (probabilistic)
NatureActivity orientedEvent oriented
DistributionNot requiredBeta distribution assumed
Suitable forRepetitive, known work such as constructionNew, research-type, uncertain work
CostTime-cost trade-off (crashing) is doneMainly time; cost is not considered
Probability of completionNot computedComputed using ZZ value
Developed byDu Pont (1957)US Navy (1958)

Calculation

te=to+4tm+tp6t_e = \dfrac{t_o + 4t_m + t_p}{6}, σ=tp−to6\sigma = \dfrac{t_p - t_o}{6}, variance =σ2= \sigma^2.

For x (4,6,84, 6, 8):

te=4+24+86=6.00σ=8−46=0.67,Var=0.44\begin{aligned} t_e &= \frac{4 + 24 + 8}{6} = 6.00 \\ \sigma &= \frac{8 - 4}{6} = 0.67, \quad \text{Var} = 0.44 \end{aligned}

For y (3,5,63, 5, 6):

te=3+20+66=4.83σ=6−36=0.50,Var=0.25\begin{aligned} t_e &= \frac{3 + 20 + 6}{6} = 4.83 \\ \sigma &= \frac{6 - 3}{6} = 0.50, \quad \text{Var} = 0.25 \end{aligned}
tet_eσ\sigmaVariance
x6.000.670.44
y4.830.500.25

Answer: tet_e(x) = 6.00 and tet_e(y) = 4.83. Activity y has the smaller SD (0.50) and variance (0.25), so y is more certain.