When to use bar chart, CPM, PERT
Short answer
Bar chart: small, simple projects (e.g., house) needing a quick, easy schedule. CPM: large, familiar projects (roads, bridges) with certain durations, needed for critical path and resource scheduling. PERT: novel, uncertain projects (hydropower tunnels, R&D) with three duration estimates, for finding completion probability.
In which situations do we have to use a bar chart, CPM and PERT for scheduling of a project?
The method is chosen according to the size of the project, nature of the activities and the certainty of the time estimates.
Bar chart
Use it when:
- the project is small, simple or has few activities (a house, a small culvert);
- a quick, easy-to-read schedule is needed for site staff or for a presentation to top management;
- the work is at the preliminary stage and the logic is not yet detailed;
- progress is to be shown to people without technical training.
CPM (Critical Path Method)
Use it when:
- the project is large and complex, with many inter-related activities, but the durations can be estimated with fair certainty from experience (roads, buildings, bridges, canals);
- the critical path and floats are needed;
- time-cost trade-off (crashing) and resource scheduling are required;
- the project is repetitive or similar projects were done before.
PERT (Programme Evaluation and Review Technique)
Use it when:
- the work is new, research-type or has no past data (first-of-its-kind hydropower, tunnelling, software, defence projects);
- activity durations are uncertain and three estimates (optimistic, most likely, pessimistic) are needed;
- the probability of finishing the project by a given date is to be found;
- the main interest is time, not cost.
| Basis | Bar chart | CPM | PERT |
|---|---|---|---|
| Project | Small, simple | Large, familiar | Large, new, uncertain |
| Time estimate | Single | Single (deterministic) | Three (probabilistic) |
| Logic shown | No | Yes | Yes |
| Critical path | No | Yes | Yes |
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Planning, scheduling; linked bar chart · Project Engineering, chapter 3
- Bar chart of irrigation project with milestones · Project Engineering, chapter 3
- Difference between CPM and PERT · Project Engineering, chapter 3 · asked 2×
- CPM and PERT and their uses · Project Engineering, chapter 3
- CPM vs PERT; te and variance for x, y · Project Engineering, chapter 3
- Planning in dynamic environment; linked bar chart · Project Engineering, chapter 3
- Bar chart vs CPM/PERT as planning tool · Construction Management, chapter 2 · asked 3×
- Difference between CPM and PERT · ICT Project Management, chapter 8
- Difference between CPM and PERT · Industrial Engineering and Management, chapter 3
- Chart vs table; bar vs pie graph · Communication English, chapter 4