Bar chart of irrigation project with milestones

Short answer

An irrigation project bar chart includes activities: survey and design (2 months), land acquisition (3), headworks (6), main canal earthwork (5), canal lining (4), canal structures (6), field channels (4), testing and handover (1). Key milestones: design approved (month 2), land ready (4), headworks complete (9), main canal complete (12), field channels complete (15), handover (16). Total project 16 months.

Prepare a bar chart of an irrigation project mentioning at least 6 activities. Also show the milestones in a chart.

Assumption: a small irrigation scheme (weir, main canal and field channels) of 16 months.

Activities and durations

CodeActivityStart (month)Duration (months)
ASurvey and design02
BLand acquisition and site clearing13
CHeadworks (weir and intake)36
DMain canal earthwork45
ECanal lining84
FCanal structures (culverts, outlets)66
GField channels and distribution114
HTesting and handover151

Bar chart (months)

                       0   4   8   12  16  (month)
                      +----------------
A Survey & design     |##              
B Land acquisition    | ###            
C Headworks (weir)    |   ######       
D Main canal earthwork|    #####       
E Canal lining        |        ####    
F Canal structures    |      ######    
G Field channels      |           #### 
H Testing, handover   |               #
                      +----------------

Milestone chart

Milestones are key events that mark completion of a major stage; * shows the planned date.

                       0   4   8   12  16 (month)
                      +----------------
M1 Design approved    | *
M2 Land ready         |   *
M3 Headworks done     |        *
M4 Main canal done    |           *
M5 Distribution done  |              *
M6 Handover           |               *
                      +----------------
MilestoneEventMonth
M1Design approved2
M2Land ready4
M3Headworks complete9
M4Main canal complete12
M5Field channels complete15
M6Handover16

The project is finished in 16 months. Land acquisition must end by month 4 and design approval by month 2; these early milestones are the main control points.