- 2072 Chaitra · 2+4 marks
Planning, scheduling; linked bar chart
Short answer
Planning defines what, how, and who; scheduling assigns when activities occur. The linked bar chart for a house project with 10 activities shows sequential and parallel work, with dependencies and 24-week project duration.
Define planning and scheduling. Prepare a linked bar chart for a construction project with at least 10 activities.
Planning and scheduling
- Planning decides what work is to be done, how (method and sequence), by whom and with what resources, to achieve the project objectives. It answers what, how, who.
- Scheduling puts the planned activities on a time scale. It fixes the start and finish date of each activity, the project duration and the float, answering when. Planning comes first; scheduling follows from it.
Linked bar chart: construction of a house (10 activities)
| Code | Activity | Duration (weeks) | Predecessor |
|---|---|---|---|
| A | Site clearing and layout | 1 | - |
| B | Excavation | 2 | A |
| C | Foundation (PCC and footing) | 3 | B |
| D | Plinth beam and DPC | 2 | C |
| E | Columns and brick walls | 5 | D |
| F | Roof slab | 3 | E |
| G | Plumbing and electrical conduits | 3 | E |
| H | Plastering | 3 | F, G |
| I | Flooring, doors and windows | 3 | H |
| J | Painting and finishing | 2 | I |
Linked bar chart (time in weeks; > shows the link from the finish of a predecessor to the start of the successor):
0 4 8 12 16 20 24 (wk)
+------------------------
A Site clearing |#>
B Excavation | ##>
C Foundation | ###>
D Plinth beam | ##>
E Walls+columns | #####>
F Roof slab | ###>
G Plumb/electric| ###>
H Plastering | ###>
I Floor,doors | ###>
J Painting | ##
+------------------------
Start times: A 0, B 1, C 3, D 6, E 8, F 13, G 13, H 16, I 19, J 22. Project duration = 22 + 2 = 24 weeks. Activities F and G are done in parallel; all others are in a series, so the chain A-B-C-D-E-F(or G)-H-I-J controls the completion.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Planning in dynamic environment; linked bar chart · Project Engineering, chapter 3
- Bar chart of irrigation project with milestones · Project Engineering, chapter 3
- Planning need, tools, bar chart limitations · Project Engineering, chapter 3
- When to use bar chart, CPM, PERT · Project Engineering, chapter 3
- Planning tools, milestone chart, WBS · Project Engineering, chapter 3
- Bar chart advantages and limitations · Project Engineering, chapter 3 · asked 2×
- Bar chart vs CPM/PERT as planning tool · Construction Management, chapter 2 · asked 3×
- TCTO numerical with time-cost chart (five activities) · Construction Management, chapter 2
- Planned maintenance, planning and scheduling · Construction Management, chapter 9 · asked 2×
- Importance and steps of planning and scheduling · Construction Management, chapter 2