- 2079 Bhadra · 8 marks
Gantt, link bar chart, milestone chart
Short answer
A Gantt chart shows activity bars with progress marking. A linked bar chart adds dependency arrows between bars to show logic. A milestone chart highlights only zero-duration key events on a timeline for top-level control. Example: in a house project, milestones might be site ready, foundation done, and structure done.
Explain in brief the Gantt chart, link bar chart and milestone chart with examples.
Example project: part of a house project (weeks).
Gantt chart
A Gantt chart shows every activity as a bar against a calendar scale and records progress inside the bar. It is used to compare planned and actual progress. Here = shows work done up to week 6 and # the work still to do.
0 4 8 12 16 (wk)
+----------------
A Site clearing |= |
B Excavation | == |
C Foundation | ===|
D Plinth beam | ##
E Walls+columns | | #####
F Roof slab | | ###
+----------------
^ status (wk 6)
At week 6, A, B and C are done, D is just starting, and E and F have not yet started.
Linked (link) bar chart
A bar chart in which arrows or links join the finish of a predecessor to the start of its successor. It shows the dependence among the activities. In the figure > shows that the next activity starts when the previous one finishes.
0 4 8 12 16 (wk)
+----------------
A Site clearing |#>
B Excavation | ##>
C Foundation | ###>
D Plinth beam | ##>
E Walls+columns | #####>
F Roof slab | ###
+----------------
Milestone chart
It shows only the key events (milestones) of the project on the time scale, such as site ready, foundation complete and structure complete. It is used by top management to see the major targets and to compare planned and forecast dates.
0 4 8 12 16 (wk)
+----------------
M1 Site ready |*
M2 Foundation done | *
M3 Structure done | *
+----------------
| Chart | Shows | Main use |
|---|---|---|
| Gantt | Activities, duration, progress | Monitoring |
| Linked bar | Activities and dependence | Planning logic |
| Milestone | Key events only | Top-level control |
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Planning tools, milestone chart, WBS · Project Engineering, chapter 3
- Gantt chart with advantages · Project Engineering, chapter 3
- Gantt chart; resource allocation and smoothing · Project Engineering, chapter 3
- Bar chart advantages and limitations · Project Engineering, chapter 3 · asked 2×
- Planning in dynamic environment; linked bar chart · Project Engineering, chapter 3
- Planning, scheduling; linked bar chart · Project Engineering, chapter 3
- Gantt chart for loading and scheduling · Industrial Engineering and Management, chapter 3
- Bar chart vs CPM/PERT as planning tool · Construction Management, chapter 2 · asked 3×
- Chart vs table; bar vs pie graph · Communication English, chapter 4
- CPU criteria; RR Gantt and times · Operating System, chapter 2