- 2068 Baisakh (old course) · 8 marks
Gantt chart; resource allocation and smoothing
Short answer
A Gantt chart is a bar chart with each activity as a horizontal bar filled in as work progresses, so planned and actual progress are compared. Resource allocation assigns manpower, machines and materials to activities. Smoothing shifts non-critical activities within float to level demand without changing project duration or critical path; limited resource allocation may delay activities and extend duration.
What is a Gantt chart? Discuss resource allocation and smoothing.
Gantt chart
A Gantt chart is a bar chart in which each activity is a horizontal bar on a time scale; the bar is filled in as work progresses, so that planned and actual progress are seen together. It is used for scheduling and monitoring.
Example (days): A excavation (3 days, 4 men), C foundation (3 days, 2 men, after A) and B fencing and store (2 days, 2 men, independent). = shows work done up to the status at the end of day 3.
0 2 4 6 (day)
+------
A Excavation |===|
C Foundation | ###
B Fencing, store |== |
+------
^ status (day 3)
Resource allocation
Resource allocation is the assignment of the available manpower, machines and materials to the activities of the schedule. The daily requirement of every activity (early start schedule) is added to get a resource aggregation chart, drawn as a resource histogram. If the demand is uneven or higher than the supply, the schedule is adjusted. Two cases occur:
- Resource levelling or smoothing (time-limited) - the project duration is fixed; activities are shifted within their float to get a smooth demand.
- Limited resource allocation (resource-limited) - the amount of resource available is fixed; activities are delayed, even beyond their float, so the duration may increase.
Resource smoothing
Smoothing is the adjustment of non-critical activities within their total float to remove peaks and valleys of the histogram without changing the project duration or the critical path.
In the example the critical chain is A-C (6 days); B has a float of 4 days. Early start histogram (B on days 1-2):
6 |# #
5 |# #
4 |# # #
3 |# # #
2 |# # # # # #
1 |# # # # # #
+------------
1 2 3 4 5 6 day
6 6 4 2 2 2 men
Peak = 6 men. Starting B on day 4 (inside its float) gives:
4 |# # # # #
3 |# # # # #
2 |# # # # # #
1 |# # # # # #
+------------
1 2 3 4 5 6 day
4 4 4 4 4 2 men
The peak falls from 6 to 4 men; total man-days (22) and the completion time (6 days) are unchanged. Benefits: steady employment, less hiring and firing, better use of equipment.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Short note: Resource allocation and smoothing · Project Engineering, chapter 3 · asked 4×
- Limited resource allocation and smoothing · Project Engineering, chapter 3
- Resource schedule; leveling vs smoothing · Project Engineering, chapter 3 · asked 2×
- Resource leveling and smoothing · Project Engineering, chapter 3
- Resource histogram, leveling, limited allocation, WBS · Project Engineering, chapter 3
- Gantt chart with advantages · Project Engineering, chapter 3
- Gantt chart for loading and scheduling · Industrial Engineering and Management, chapter 3
- CPU criteria; RR Gantt and times · Operating System, chapter 2
- FCFS, SJF, Priority, RR Gantt; max AWT · Operating System, chapter 2
- Preemptive priority and SRTF Gantt · Operating System, chapter 2