Resource leveling and smoothing

Short answer

Resource leveling reschedules activities to make daily resource demand uniform and within availability; it may delay activities beyond float and increase project duration. Resource smoothing adjusts only non-critical activities within float to reduce peaks without changing project duration.

Define resource leveling and smoothing.

Resource levelling is the rescheduling of activities so that the daily demand for a resource becomes as uniform as possible and does not exceed the amount available. Non-critical activities are first shifted within their float; if the demand still exceeds the limit, activities are delayed beyond their float, so the project duration may increase (resource-limited).

Resource smoothing is the adjustment of non-critical activities only within their float, to reduce the peaks and valleys of the resource histogram, without changing the project duration or the critical path (time-limited).

(Some textbooks use the term levelling for the time-limited case as well; the key difference is whether the project duration is held fixed.)

✓ Answer checked by Claude Opus 5.5 (high effort)

All Project Engineering chapter 3 questions →