- 2082 Bhadra · 5 marks
Limited resource allocation and smoothing
Short answer
Limited resource allocation schedules activities so daily demand never exceeds a fixed resource limit, delaying activities and possibly increasing project duration. Resource smoothing shifts non-critical activities within float to reduce peaks while keeping duration fixed. In construction, they set gang sizes, equipment numbers and cash limits.
Define limited resource allocation and resource smoothing. Explain their application for scheduling of a construction project.
Limited resource allocation
When the amount of a resource (masons, excavators, cement, cash) available per day has an upper limit, the activities must be scheduled so that the daily demand never exceeds that limit. Activities are delayed (even beyond their float) if necessary, so the project duration may increase. Method (heuristic):
- Draw the early-start schedule and find float of each activity.
- For each day, add the demand of the activities that can start.
- If demand is above the limit, give priority to the activity with the least float (smallest LST), i.e. critical ones first, and delay the others.
- Update the schedule day by day until all activities are scheduled.
Resource smoothing
Resource smoothing adjusts non-critical activities within their float to reduce peaks, keeping the project duration. It is used when the duration is fixed (time-limited).
Application to a construction project
Example: A foundation excavation (3 days, 3 men), D footing after A (2 days, 2 men), B fencing (2 days, 2 men), C material shed (2 days, 3 men). Critical path A-D (5 days). Early start demand is 8 men on days 1-2.
Limit 5 men: A and B start on day 1; C (float 3 days) is moved to days 4-5 with D.
5 |# # # #
4 |# # # #
3 |# # # # #
2 |# # # # #
1 |# # # # #
+----------
1 2 3 4 5 day
5 5 3 5 5 men
The duration remains 5 days, and the peak falls from 8 to 5 men.
Limit 4 men: A on days 1-3; B and D on days 4-5; C on days 6-7.
4 | # #
3 |# # # # # # #
2 |# # # # # # #
1 |# # # # # # #
+--------------
1 2 3 4 5 6 7 day
3 3 3 4 4 3 3 men
Now the duration increases from 5 to 7 days.
Used in building, road and canal works to decide gang size, equipment number and cash limits, and to find the realistic completion time.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Short note: Resource allocation and smoothing · Project Engineering, chapter 3 · asked 4×
- Gantt chart; resource allocation and smoothing · Project Engineering, chapter 3
- Resource histogram, leveling, limited allocation, WBS · Project Engineering, chapter 3
- Resource schedule; leveling vs smoothing · Project Engineering, chapter 3 · asked 2×
- Resource leveling and smoothing · Project Engineering, chapter 3
- Internal risk of Nepalese construction project · Project Engineering, chapter 5
- Isolator construction, principle and application · Switchgear and Protection, chapter 4
- Characteristics of a construction project · Construction Management, chapter 1