Resource schedule; leveling vs smoothing

Short answer

A resource schedule shows resource requirements per time period. Resource levelling adjusts activities to keep demand within a fixed resource limit, possibly extending duration. Resource smoothing adjusts non-critical activities within float to make demand uniform without altering project duration.

Define resource schedule. Differentiate between resource levelling and resource smoothing.

A resource schedule shows how many units of each resource (manpower, equipment, materials, money) are needed in each time period of the project, based on the activity schedule. It is shown by a resource histogram or table.

BasisResource levellingResource smoothing
ConstraintResource limit is fixed (resource-constrained)Project duration is fixed (time-constrained)
AimKeep demand within the available limitMake demand as uniform as possible
Project durationMay increaseDoes not change
Float usedTotal float, and critical activities may also be delayedOnly available float of non-critical activities
Critical activitiesMay be delayedNot changed
Used whenResources are scarceDeadline is rigid and demand is uneven