Gantt chart with advantages

Short answer

A Gantt chart displays activities as bars on a time scale, comparing planned and actual progress. Advantages: simple to prepare and read, shows start/finish/duration of each activity, enables direct progress comparison, aids resource planning, and is easily understood by all stakeholders.

Draw a Gantt chart of a project having at least 10 activities. Write its advantages.

Gantt chart

A Gantt chart is a bar chart in which each activity is drawn as a horizontal bar on a time scale; the bar is filled in as the work progresses, so that planned and actual progress can be compared. Example: house project of 10 activities (progress shown at the end of week 10; # = planned, = = work done, | = status date).

CodeActivityDuration (weeks)Predecessor
ASite clearing and layout1-
BExcavation2A
CFoundation (PCC and footing)3B
DPlinth beam and DPC2C
EColumns and brick walls5D
FRoof slab3E
GPlumbing and electrical conduits3E
HPlastering3F, G
IFlooring, doors and windows3H
JPainting and finishing2I
                 0   4   8   12  16  20  24 (wk)
                +------------------------
A Site clearing |=         |             
B Excavation    | ==       |             
C Foundation    |   ===    |             
D Plinth beam   |      ==  |             
E Walls+columns |        ==###           
F Roof slab     |          |  ###        
G Plumb/electric|          |  ###        
H Plastering    |          |     ###     
I Floor,doors   |          |        ###  
J Painting      |          |           ##
                +------------------------
                           ^ status (wk 10)

Reading at week 10: A, B, C and D are complete (on plan); E (walls) has done 2 of its 5 weeks (planned: it started at week 8, so it is on schedule); the rest have not started. Total duration is 24 weeks.

Advantages

  • Very simple to prepare, read and understand.
  • Shows start, finish and duration of each activity and the total project time on one page.
  • Planned and actual progress are compared directly, so delay is seen quickly.
  • Good tool for communication with the client, management and site staff.
  • Helps in planning of manpower, machine and material on a time scale.
  • Cheap; no training or computer is needed.