- 2070 Chaitra (old course) · 6+2 marks
Gantt chart with advantages
Short answer
A Gantt chart displays activities as bars on a time scale, comparing planned and actual progress. Advantages: simple to prepare and read, shows start/finish/duration of each activity, enables direct progress comparison, aids resource planning, and is easily understood by all stakeholders.
Draw a Gantt chart of a project having at least 10 activities. Write its advantages.
Gantt chart
A Gantt chart is a bar chart in which each activity is drawn as a horizontal bar on a time scale; the bar is filled in as the work progresses, so that planned and actual progress can be compared. Example: house project of 10 activities (progress shown at the end of week 10; # = planned, = = work done, | = status date).
| Code | Activity | Duration (weeks) | Predecessor |
|---|---|---|---|
| A | Site clearing and layout | 1 | - |
| B | Excavation | 2 | A |
| C | Foundation (PCC and footing) | 3 | B |
| D | Plinth beam and DPC | 2 | C |
| E | Columns and brick walls | 5 | D |
| F | Roof slab | 3 | E |
| G | Plumbing and electrical conduits | 3 | E |
| H | Plastering | 3 | F, G |
| I | Flooring, doors and windows | 3 | H |
| J | Painting and finishing | 2 | I |
0 4 8 12 16 20 24 (wk)
+------------------------
A Site clearing |= |
B Excavation | == |
C Foundation | === |
D Plinth beam | == |
E Walls+columns | ==###
F Roof slab | | ###
G Plumb/electric| | ###
H Plastering | | ###
I Floor,doors | | ###
J Painting | | ##
+------------------------
^ status (wk 10)
Reading at week 10: A, B, C and D are complete (on plan); E (walls) has done 2 of its 5 weeks (planned: it started at week 8, so it is on schedule); the rest have not started. Total duration is 24 weeks.
Advantages
- Very simple to prepare, read and understand.
- Shows start, finish and duration of each activity and the total project time on one page.
- Planned and actual progress are compared directly, so delay is seen quickly.
- Good tool for communication with the client, management and site staff.
- Helps in planning of manpower, machine and material on a time scale.
- Cheap; no training or computer is needed.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Gantt, link bar chart, milestone chart · Project Engineering, chapter 3
- Gantt chart; resource allocation and smoothing · Project Engineering, chapter 3
- Bar chart of irrigation project with milestones · Project Engineering, chapter 3
- Project life cycle phases and activities · Project Engineering, chapter 1 · asked 5×
- Project attributes; implementation phase activities · Project Engineering, chapter 1
- Is a specified job a project? Implementation activities · Project Engineering, chapter 1
- Gantt chart for loading and scheduling · Industrial Engineering and Management, chapter 3
- TCTO numerical with time-cost chart (five activities) · Construction Management, chapter 2
- CPU criteria; RR Gantt and times · Operating System, chapter 2
- FCFS, SJF, Priority, RR Gantt; max AWT · Operating System, chapter 2