Difference between CPM and PERT

Short answer

CPM uses a single deterministic time estimate for activities, is activity-oriented, and suitable for repetitive projects. PERT uses three time estimates (optimistic, most likely, pessimistic) to calculate expected time and variance probabilistically, and is event-oriented for uncertain projects.

What is the difference between CPM and PERT?

CPM (Critical Path Method) and PERT (Program Evaluation and Review Technique) are network-based scheduling techniques that identify the critical path. CPM was developed in 1957 (DuPont) for construction/industrial projects; PERT was developed in 1958 (US Navy, Polaris missile) for R&D projects.

BasisCPMPERT
Time estimateOne deterministic estimateThree estimates: optimistic (a), most likely (m), pessimistic (b)
NatureDeterministicProbabilistic
Expected timeSingle duration givente = (a + 4m + b) / 6
VarianceNot consideredσ² = ((b − a)/6)²
OrientationActivity-orientedEvent-oriented
UseRepetitive, well-known projects (construction, maintenance)Non-repetitive, uncertain projects (R&D, new software)
CostConsiders time-cost trade-off (crashing)Mainly time; cost is secondary
ProbabilityCannot find probability of completionFinds probability of completing by a date using normal distribution
FocusControlling costControlling time
NetworkActivity on arrow or nodeMostly activity on arrow
DistributionNoneBeta distribution assumed

Common points

Both use network diagrams, identify critical path and float, need a WBS and activity dependencies, and support planning and control.

Example of PERT numbers

a = 4, m = 6, b = 14 days: te = (4 + 24 + 14)/6 = 7 days; σ = (14 − 4)/6 = 1.67 days.

CPM:  Activity -> single time -> critical path
PERT: Activity -> a, m, b -> te, variance -> probability

Modern software often uses CPM-style calculations with PERT estimates for uncertain tasks.