Difference between CPM and PERT
Short answer
CPM uses a single deterministic duration and is activity-oriented, allowing time-cost trade-off. PERT uses three time estimates (optimistic, most likely, pessimistic) to compute expected time and is event-oriented, suitable for projects with high uncertainty.
Differentiate between CPM and PERT.
| Basis | CPM | PERT |
|---|---|---|
| Full form | Critical Path Method | Programme Evaluation and Review Technique |
| Origin | DuPont, 1957, construction and plant maintenance | US Navy, 1958, Polaris missile project |
| Time estimate | One deterministic time | Three times: optimistic , most likely , pessimistic |
| Nature | Deterministic | Probabilistic |
| Expected time | Given duration | |
| Basis | Activity oriented | Event oriented |
| Cost | Time-cost trade-off (crashing) considered | Mainly time; cost not usually considered |
| Suitable for | Repetitive, known work (construction) | Research, development and new projects with uncertainty |
| Output | Critical path and float | Critical path and probability of finishing by a date |
| Network | Activity-on-arrow or activity-on-node; dummies needed only in activity-on-arrow | Event-based activity-on-arrow network; dummies used where needed |
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- When to use bar chart, CPM, PERT · Project Engineering, chapter 3
- CPM and PERT and their uses · Project Engineering, chapter 3
- CPM vs PERT; te and variance for x, y · Project Engineering, chapter 3
- Difference between CPM and PERT · ICT Project Management, chapter 8
- Difference between CPM and PERT · Industrial Engineering and Management, chapter 3
- Bar chart vs CPM/PERT as planning tool · Construction Management, chapter 2 · asked 3×