Difference between CPM and PERT

Short answer

CPM uses a single deterministic duration and is activity-oriented, allowing time-cost trade-off. PERT uses three time estimates (optimistic, most likely, pessimistic) to compute expected time and is event-oriented, suitable for projects with high uncertainty.

Differentiate between CPM and PERT.

BasisCPMPERT
Full formCritical Path MethodProgramme Evaluation and Review Technique
OriginDuPont, 1957, construction and plant maintenanceUS Navy, 1958, Polaris missile project
Time estimateOne deterministic timeThree times: optimistic aa, most likely mm, pessimistic bb
NatureDeterministicProbabilistic
Expected timeGiven durationte=a+4m+b6t_e = \dfrac{a + 4m + b}{6}
BasisActivity orientedEvent oriented
CostTime-cost trade-off (crashing) consideredMainly time; cost not usually considered
Suitable forRepetitive, known work (construction)Research, development and new projects with uncertainty
OutputCritical path and floatCritical path and probability of finishing by a date
NetworkActivity-on-arrow or activity-on-node; dummies needed only in activity-on-arrowEvent-based activity-on-arrow network; dummies used where needed