- 2065 Shrawan (old course) · 5 marks
CPM and PERT and their uses
Short answer
CPM uses deterministic time estimates to find the critical path, project duration and floats, and supports time-cost trade-off, suitable for construction projects with known durations. PERT uses three probabilistic time estimates (optimistic, most likely, pessimistic) to find expected duration and probability of completion, suitable for research and development projects with uncertain times.
Explain CPM and PERT and their uses.
CPM (Critical Path Method)
CPM was developed in 1957 by Du Pont and Remington Rand for plant maintenance and construction. It is a network technique with deterministic (single) time estimates for each activity. It finds the critical path, project duration and floats, and links time with cost (cost-time trade-off).
PERT (Programme Evaluation and Review Technique)
PERT was developed in 1958 by the US Navy for the Polaris missile project. It is probabilistic: three time estimates are used - optimistic , most likely and pessimistic .
It is event oriented and gives the probability of finishing by a given date.
Uses
| CPM | PERT |
|---|---|
| Construction projects (roads, buildings, bridges) with known durations | Research, development and new, first-time projects |
| Finding critical path and floats | Estimating the chance of meeting a deadline |
| Time-cost trade-off and crashing | Projects where time estimates are uncertain |
| Resource levelling and scheduling | Planning and review of big programmes such as defence and hydropower tunnelling |
| Monitoring and updating the schedule | Control of time (cost is not the main concern) |
Both help to plan, schedule and control large projects, show inter-dependence of activities, and focus management attention on critical activities.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Difference between CPM and PERT · Project Engineering, chapter 3 · asked 2×
- When to use bar chart, CPM, PERT · Project Engineering, chapter 3
- CPM vs PERT; te and variance for x, y · Project Engineering, chapter 3
- PERT mean and SD of two projects · Project Engineering, chapter 3
- Bar chart vs CPM/PERT as planning tool · Construction Management, chapter 2 · asked 3×
- Difference between CPM and PERT · ICT Project Management, chapter 8
- Difference between CPM and PERT · Industrial Engineering and Management, chapter 3