PERT mean and SD of two projects

Short answer

Using PERT formulas, mean = (t_o+4t_m+t_p)/6 and SD = (t_p–t_o)/6. For Project A: mean 8.17, SD 1.17; for Project B: mean 8.17, SD 0.83. Both have the same expected time, but Project B is more certain because of its smaller standard deviation.

Define PERT and discuss its uses. Project A and B have to, tm and tp as 5, 8, 12 and 6, 8, 11 respectively. Find the mean and standard deviation. Which project is better and more certain?

PERT

PERT is a probabilistic network technique used when activity times are uncertain. Three estimates are made for each activity: optimistic tot_o, most likely tmt_m, pessimistic tpt_p.

te=to+4tm+tp6,σ=tp−to6t_e = \frac{t_o + 4t_m + t_p}{6}, \qquad \sigma = \frac{t_p - t_o}{6}

Uses:

  • planning and control of new, research and development or first-time projects with uncertain durations;
  • finding the expected project duration and the probability of finishing by a due date;
  • identifying critical activities with large variance for special attention;
  • scheduling, coordination and review of large programmes (event-oriented control).

Calculation

Project A (to=5, tm=8, tp=12t_o=5,\ t_m=8,\ t_p=12):

te=5+4(8)+126=496=8.17σ=12−56=1.17,Variance=1.36\begin{aligned} t_e &= \frac{5 + 4(8) + 12}{6} = \frac{49}{6} = 8.17 \\ \sigma &= \frac{12 - 5}{6} = 1.17, \quad \text{Variance} = 1.36 \end{aligned}

Project B (to=6, tm=8, tp=11t_o=6,\ t_m=8,\ t_p=11):

te=6+4(8)+116=496=8.17σ=11−66=0.83,Variance=0.69\begin{aligned} t_e &= \frac{6 + 4(8) + 11}{6} = \frac{49}{6} = 8.17 \\ \sigma &= \frac{11 - 6}{6} = 0.83, \quad \text{Variance} = 0.69 \end{aligned}
ProjectMean tet_eSD σ\sigmaVariance
A8.171.171.36
B8.170.830.69

Both have the same expected time (8.17), but B has the smaller standard deviation and variance. So project B is better and more certain, because its completion time is less scattered about the mean, so the risk of delay is lower.

Answer: mean 8.17 for both; SD 1.17 (A) and 0.83 (B); project B is preferred.