- Practice · 5 marks
Difference between CPM and PERT
Short answer
CPM uses deterministic time estimates for repetitive projects, while PERT uses three probabilistic estimates for uncertain R&D projects. Critical path is the longest path determining project duration. Float is delay allowed without delaying project; event slack is difference between latest and earliest event times in PERT.
Differentiate between CPM and PERT. Explain the terms critical path, float and event slack.
Both CPM (Critical Path Method, DuPont 1957) and PERT (Program Evaluation and Review Technique, US Navy, Polaris project 1958) are network techniques for planning, scheduling and controlling projects.
| Basis | CPM | PERT |
|---|---|---|
| Origin | Industrial/construction projects | Research and development projects |
| Time estimate | One deterministic time | Three estimates: a, m, b |
| Nature | Deterministic | Probabilistic |
| Orientation | Activity oriented | Event oriented |
| Cost | Time-cost trade-off (crashing) is considered | Mainly time; cost not considered |
| Use | Repetitive, well-known jobs | Non-repetitive, uncertain jobs |
| Probability | Not computed | Probability of meeting a date is found |
| Distribution | Not used | Beta distribution |
Terms
- Critical path: the longest path through the network; it fixes the shortest possible project duration. Any delay in a critical activity delays the whole project.
- Total float: the time by which an activity can be delayed without delaying the project completion: . Critical activities have zero float.
- Free float: delay possible without affecting the earliest start of the next activity.
- Event slack (PERT): for an event, , the difference between latest allowable and earliest expected event times. Events on the critical path have zero slack.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3
- Difference between CPM and PERT · ICT Project Management, chapter 8
- Difference between CPM and PERT · Project Engineering, chapter 3 · asked 2×
- Dummy activity; use of critical path in CPM · Project Engineering, chapter 3
- Bar chart vs CPM/PERT as planning tool · Construction Management, chapter 2 · asked 3×