- 2076 Chaitra · 1+3 marks
Dummy activity; use of critical path in CPM
Short answer
A dummy is a zero-duration, zero-resource activity drawn as a dashed arrow to show logical dependence or give unique event numbers. The critical path in CPM gives the minimum project duration, identifies zero-float critical activities needing priority control, guides crashing, and allows float on non-critical activities for resource levelling.
What is a dummy activity? Write down the use of critical path in a CPM network diagram.
Dummy activity
A dummy activity is an activity of zero duration and no resource, drawn as a dashed arrow, used in an arrow diagram to show logical dependence or to give unique event numbers.
Use of critical path in a CPM network
- Gives the minimum time to complete the project (the length of the longest path).
- Identifies the critical activities that have no float; they need close control and priority in resources.
- Shows that a delay of a critical activity delays the whole project, so delay is predicted and corrected early.
- To shorten the project duration (crashing), only the critical path is shortened.
- Non-critical activities have float, which is used for resource levelling and flexible scheduling.
- Helps in cost-time trade-off and in updating the schedule during execution.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Critical path and dummy activity significance · Project Engineering, chapter 3
- CPM network, 9 activities (A=3 to I=1) · Project Engineering, chapter 3 · asked 5×
- CPM network, 9 activities (A=5 to I=2) · Project Engineering, chapter 3 · asked 5×
- CPM network, 13 activities (A to M) · Project Engineering, chapter 3 · asked 5×
- CPM network, 13 activities (A=2 to M=7) · Project Engineering, chapter 3 · asked 5×
- Dummy activity and its application · Project Engineering, chapter 3
- CPM schedule, critical path and float · Industrial Engineering and Management, chapter 3
- TCTO numerical: crashing critical path, Rs 30/day · Construction Management, chapter 2
- Essential components of an activity diagram · Object Oriented Analysis and Design, chapter 2