CPM network, 9 activities (A=5 to I=2)

Short answer

Project duration is 20 weeks; critical path is A-C-E-G-I. EST/EFT/LST/LFT computed by forward/backward pass; total floats: A,C,E,G,I zero, B and D 1, F and H 2.

Draw the CPM network diagram and compute EST, EFT, LST, LFT, TF, FF, Int.F and Ind.F from the information given below. Also compute the project duration and mark the critical path.

ActivityDuration (week)Predecessor
A5-
B4-
C0A
D6A
E7B, C
F8B, C
G6D, E
H3F
I2G, H

Notation: EST/EFT = earliest start/finish, LST/LFT = latest start/finish, TF = total float, FF = free float, Int.F = interfering float, Ind.F = independent float.

Network diagram (activity-on-arrow)

Each activity is an arrow with its duration in brackets (weeks). Events are circled numbers; dashed arrows are dummy activities (zero duration) that show dependencies only.

(1) --A(5)--> (2)
(1) --B(4)--> (3)
(2) --C(0)--> (3)
(2) --D(6)--> (4)
(3) --E(7)--> (4)
(3) --F(8)--> (5)
(4) --G(6)--> (6)
(5) --H(3)--> (6)
(6) --I(2)--> (7)

The network has 7 events and 0 dummy activities. Start event is (1) and the end event is (7).

Activity C has zero duration, so it is treated as a normal activity of 0 weeks (it only passes the logic on).

Forward pass (EST and EFT)

Rule: EST = largest EFT of the preceding activities (0 for start activities); EFT = EST + D.

  • A: EST = 0; EFT = 0 + 5 = 5
  • B: EST = 0; EFT = 0 + 4 = 4
  • C: EST = EFT of A = 5; EFT = 5 + 0 = 5
  • D: EST = EFT of A = 5; EFT = 5 + 6 = 11
  • E: EST = max(B:4, C:5) = 5; EFT = 5 + 7 = 12
  • F: EST = max(B:4, C:5) = 5; EFT = 5 + 8 = 13
  • G: EST = max(D:11, E:12) = 12; EFT = 12 + 6 = 18
  • H: EST = EFT of F = 13; EFT = 13 + 3 = 16
  • I: EST = max(G:18, H:16) = 18; EFT = 18 + 2 = 20

Project duration = largest EFT = 20 weeks.

Backward pass (LFT and LST)

Rule: LFT = smallest LST of the succeeding activities (project duration for end activities); LST = LFT - D.

  • I: LFT = project duration = 20; LST = 20 - 2 = 18
  • H: LFT = LST of I = 18; LST = 18 - 3 = 15
  • G: LFT = LST of I = 18; LST = 18 - 6 = 12
  • F: LFT = LST of H = 15; LST = 15 - 8 = 7
  • E: LFT = LST of G = 12; LST = 12 - 7 = 5
  • D: LFT = LST of G = 12; LST = 12 - 6 = 6
  • C: LFT = min(E:5, F:7) = 5; LST = 5 - 0 = 5
  • B: LFT = min(E:5, F:7) = 5; LST = 5 - 4 = 1
  • A: LFT = min(C:5, D:6) = 5; LST = 5 - 5 = 0

Floats

  • Total float TF=LST−EST=LFT−EFTTF = LST - EST = LFT - EFT
  • Free float FF=min⁡(EST of successors)−EFTFF = \min(\text{EST of successors}) - EFT
  • Interfering float IntF=TF−FFIntF = TF - FF
  • Independent float IndF=max⁡(0, min⁡(EST of successors)−max⁡(LFT of predecessors)−D)IndF = \max\left(0,\ \min(\text{EST of successors}) - \max(\text{LFT of predecessors}) - D\right)

Result table

ActivityDESTEFTLSTLFTTFFFInt.FInd.F
A505050000
B404151101
C055550000
D65116121101
E75125120000
F85137152020
G6121812180000
H3131615182200
I2182018200000

Event times (TE from the forward pass, TL from the backward pass):

EventTE (earliest)TL (latest)Slack
1000
2550
3550
412120
513152
618180
720200

Critical path and project duration

  • Critical activities (TF = 0): A, C, E, G, I
  • Critical path: A - C - E - G - I (= 5+0+7+6+2 = 20 weeks)

Answer: project duration = 20 weeks; critical path = A - C - E - G - I